1. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A. Total float
B. Free float
C. Interfering float
D. Independent float
Answer : D
2. Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
Answer : B
3. Whenever an activity has zero total float, then
A. Free float of the activity must be zero but independent float need not be zero
B. Independent float must be zero but free float need not be zero
C. Free float and independent float both must be zero
D. Free float and independent float both need not be zero
Answer : C
4. The technique for establishing and maintaining priorities among the various jobs of a project, is known
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
Answer : B
5. In PERT analysis, the time estimates of activities and probability of their occurrence follow
A. Normal distribution curve
B. Poisson's distribution curve
C. Beta distribution curve
D. None of the above
Answer : C
6. The time with which direct cost does not reduce with the increase in time is known as
A. Crash time
B. Normal time
C. Optimistic time
D. Standard time
Answer : B
7. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
A. Moist loam
B. Good common earth
C. Well blasted rock
D. Wet sticky clay
Answer : A
8. Power stations are generally treated as
A. Light construction
B. Heavy construction
C. Industrial construction
D. Electrical construction
Answer : C
9. The time corresponding to minimum total project cost is
A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
Answer : D
10. Military organisation is known as
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. None of these
Answer : A
11. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
A. EF = ES + D
B. LS = LF - D
C. LF = LS + D
D. All the above
Answer : D
12. During the construction period, price variation clause in contracts caters to
A. Increase in rates of only important materials
B. Variation in cost in materials element, labour element and petrol-oillubricant element
C. Variation in total cost of the project on an ad hoc basis
D. Rate of inflation
Answer : B
13. Time and progress chart of a construction, is also known as
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. All the above
Answer : D
14. Updating may result in
A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
D. All of the above
Answer : D
15. A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
Answer : D
16. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Assistant Engineer
Answer : B
17. A Milestone chart
A. Shows the interdependencies of various jobs
B. Depicts the delay of jobs, if any
C. Points outgoing ahead of schedule of jobs, if any
D. None of these
Answer : D
18. A golden rule for the procurement of construction stones, suggests
A. 100% at the site
B. 67% at the site and 33% under procurement
C. 50% at the site and 50% under procurement
D. 33% at the site and 67% under procurement
Answer : B
19. Pre-tender stage requires
A. Acquisition of land
B. Selection of site
C. Fmalisation of alignment of work
D. All the above
Answer : D
20. At a work site, statistical quality control of concrete means
A. Measurement of risks to eliminate failures
B. Applying the theory' of probability to sample testing or inspection
C. Reduction in wastage of inspection costs
D. Reduction in costs for the removal of defects
Answer : B
21. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
Answer : D
22. In CPM analysis,
A. Emphasis is given to activities
B. Uncertainties are not allowed
C. Activities are represented by arrows
D. All the above
Answer : D
23. A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects
B. Could invest in either of the two projects
C. Should invest in project A
D. Should invest in project B
Answer : A
24. Which one of the following represents an activity?
A. Excavation for foundation
B. Curing of concrete
C. Setting of question paper
D. All the above
Answer : D
25. An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
A. Rs. 8,43,750
B. Rs. 8,75,000
C. Rs. 10,50,000
D. Rs. 11,56,250
Answer : A
26. The salient feature of functional organisation is
A. Strict adherence to specifications
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All the above
Answer : D
27. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
A. (t1 - t2) - t
B. t - (t1 - t2)
C. (t1 + t2) - t
D. t + (t1 - t2)
Answer : A
28. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer : C
29. Pick up the correct statement from the following:
A. Earliest expected time is denoted by TE
B. Latest occurrence time is denoted by TL
C. Contractual obligation time is denoted by Ts
D. All the above
Answer : D
30. If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum
Answer : A
31. A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
A. Rs. 1740
B. Rs. 3480
C. Rs. 5220
D. Rs. 6960
Answer : B
32. Which of the following does not represent an activity?
A. Site located
B. Foundation is being dug
C. The office area is being cleaned
D. The invitations are being sent
Answer : A
33. Which of the following excavators is most suitable for digging under water?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Answer : A
34. Critical path lies along the activities having total float
A. Positive
B. Negative
C. Zero
D. Same
Answer : C
35. PERT technique of network analysis is mainly useful for
A. Small projects
B. Large and complex projects
C. Research and development projects
D. Deterministic activities
Answer : C
36. Sinking fund is
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
Answer : A
37. Which one of the following represents an event?
A. Concrete cured
B. Fixing of door
C. Plastering of walls
D. Selecting sites
Answer : A
38. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
Answer : A
39. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20
B. 25
C. 35
D. 15
Answer : B
40. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
A. 80 and 90
B. 90 and 80
C. 85 and 75
D. 75 and 83
Answer : D
41. Critical path method
A. Is an improvement upon bar chart method
B. Provides a realistic approach to daily problems
C. Avoids delays which are very common in bar charts
D. All the above
Answer : D
42. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
A. 20 kg/tonne
B. 30 kg/tonne
C. 40 kg/tonne
D. 50 kg/tonne
Answer : C
43. The main advantage of line organisation is:
A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
D. All the above
Answer : D
44. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
45. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A. 8 days
B. 9 days
C. 10 days
D. 15 days
Answer : B
46. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
A. Ice
B. Concrete
C. Loose sand
D. Earth
Answer : D
47. The final selection of a construction site, is done by
A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
D. All the above
Answer : D
48. Mobilization advance up to 10% of the cost of work is given to a contractor
A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and other staff
D. For all activities required to start the work at site on finalization of the contract document
Answer : D
49. The probability of completion of any activity within its expected time is
A. 50 %
B. 84.1 %
C. 99.9 %
D. 100 %
Answer : A
50. The most popular type of organisation used for Civil Engineering Constructions, is
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : A