1. PERT technique of network analysis is mainly useful for
A. Small projects
B. Large and complex projects
C. Research and development projects
D. Deterministic activities
Answer : C
2. The final selection of a construction site, is done by
A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
D. All the above
Answer : D
3. The salient feature of functional organisation is
A. Strict adherence to specifications
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All the above
Answer : D
4. While filling the tender for any work, the contractor considers
A. Site survey
B. Availability of construction materials
C. Availability of labour
D. All the above
Answer : D
5. Completion of an activity on CPM network diagram, is generally known
A. Event
B. Node
C. Connector
D. All the above
Answer : D
6. During the construction period, price variation clause in contracts caters to
A. Increase in rates of only important materials
B. Variation in cost in materials element, labour element and petrol-oillubricant element
C. Variation in total cost of the project on an ad hoc basis
D. Rate of inflation
Answer : B
7. Pick up the correct statement from the following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. In CPM, the time is related to cost
D. All the above
Answer : D
8. While scheduling a project by C.P.M.
A. A project is divided into various activities
B. Required time for each activity is established
C. Net work is drawn by connecting the activities and the events
D. All the above
Answer : D
9. Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4
B. 3, 1, 4, 2
C. 3, 1, 2, 4
D. 1, 3, 4, 2
Answer : C
10. The main disadvantage of line organisation, is
A. Rigid structure
B. Extraordinary delay in communications
C. Top level executions over work
D. All the above
Answer : D
11. Pick up the incorrect statement from the following:
A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
B. The difference between the maximum time available for the job and actual time it consumes, is called total float
C. The difference between the latest start time and earliest start time of an activity, is called total float
D. None of these
Answer : D
12. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A. 8 days
B. 9 days
C. 10 days
D. 15 days
Answer : B
13. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
A. 80 and 90
B. 90 and 80
C. 85 and 75
D. 75 and 83
Answer : D
14. The most popular type of organisation used for Civil Engineering Constructions, is
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : A
15. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
A. 20 kg/tonne
B. 30 kg/tonne
C. 40 kg/tonne
D. 50 kg/tonne
Answer : C
16. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
17. Frederick W. Taylor introduced a system of working known as
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : C
18. Pick up the correct statement from the following:
A. Earliest expected time is denoted by TE
B. Latest occurrence time is denoted by TL
C. Contractual obligation time is denoted by Ts
D. All the above
Answer : D
19. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
A. Ice
B. Concrete
C. Loose sand
D. Earth
Answer : D
20. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A. Total float
B. Free float
C. Interfering float
D. Independent float
Answer : D
21. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer : C
22. Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.
A. Both A and R is true and R is the correct explanation of A
B. Both A and R is true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
Answer : A
23. An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
A. Rs. 8,43,750
B. Rs. 8,75,000
C. Rs. 10,50,000
D. Rs. 11,56,250
Answer : A
24. The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
A. Rs. 8,800
B. Rs. 7,600
C. Rs. 6,400
D. Rs. 5,000
Answer : C
25. The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
A. 3425 kg
B. 5515 kg
C. 4350 kg
D. 2975 kg
Answer : B
26. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
Answer : D
27. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
D. All the above
Answer : D
28. Which one of the following represents an event?
A. Concrete cured
B. Fixing of door
C. Plastering of walls
D. Selecting sites
Answer : A
29. Various activities of a project, are shown on bar charts by
A. Vertical lines
B. Horizontal lines
C. Dots
D. Crosses
Answer : B
30. The basic action involved in sheep foot rolling is
A. Kneading
B. Pressing
C. Tamping
D. Vibration
Answer : A
31. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
Answer : A
32. Which of the following is a weakness of bar chart?
A. Interdependencies of activities
B. Project progress
C. Uncertainties
D. All of the above
Answer : D
33. A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
C. Does not consume time
D. All the above
Answer : D
34. PERT analysis is based on
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All the above
Answer : D
35. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
A. to + 3tm+ tp/3
B. to + 4tm+ tp/4
C. to + 4tm+ tp/5
D. to + 4tm+ tp/6
Answer : D
36. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
A. 4 days
B. 6 days
C. 10 days
D. 16 days
Answer : D
37. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Assistant Engineer
Answer : B
38. If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum
Answer : A
39. Sinking fund is
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
Answer : A
40. Mobilization advance up to 10% of the cost of work is given to a contractor
A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and other staff
D. For all activities required to start the work at site on finalization of the contract document
Answer : D
41. The main principle of an organisation, is
A. Unity of command
B. Effective control at all levels
C. Delegation of authority
D. All the above
Answer : D
42. Pick up the correct statement from the following:
A. Programme Evaluation and Review Technique, is event oriented
B. Programme Evaluation and Review Technique is not event oriented
C. Critical Path Method is event oriented
D. Critical Path method is event oriented
Answer : A
43. Select the incorrect statement.
A. Start float and finish float are always equal.
B. Total float can be either start float or finish float.
C. Start float and finish float need not be equal.
D. Start float and finish float are the differences between activity times and not event times.
Answer : C
44. Henry Gantt developed Bar charts for planning and scheduling of projects in
A. 1880
B. 1900
C. 1920
D. 1940
Answer : B
45. Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements

A. 1, 3 and 4 are correct
B. 2, 3 and 4 are correct
C. 1, 2 and 3 are correct
D. 1, 2 and 4 are correct
Answer : C
46. In the given figure, the network of a project represents

A. Activity of an excavation of a footing
B. Activity of an excavation which starts at event No. 1 and ends at even No. 2
C. Activity of excavation which takes 8 units of time
D. None of these
Answer : C
47. Pick up the correct statement from the following:
A. Optimistic time estimate refers to activities
B. Pessimistic time estimate refers to activities
C. Most likely time estimate refers to activities
D. All the above
Answer : D
48. Grader is used mainly for
A. Trimming and finishing
B. Shaping and trimming
C. Finishing and shaping
D. Finishing, shaping and trimming
Answer : D
49. The first stage of a construction, is
A. Preparation of estimate
B. Survey of the site
C. Initiation of proposal
D. Preparation of tender
Answer : C
50. The direct cost of a project with respect to normal time is
A. Minimum
B. Maximum
C. Zero
D. Infinite
Answer : A