1000+ Industrial Engineering & Production Management Test MCQ for SSC CHSL [Solved]

Thursday 9th of March 2023

Sharing is caring

1. If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be
A. TR
B. TR + [(S - T)/2] × R
C. TR + (S - T) × R
D. TR + [(S - T)/S] × R
Answer : D
2. Pick up the correct step used for scheduling a project by C.P.M.
A. A project is divided into various activities
B. Required time for each activity is established
C. Sequence of various activities is made according to their importance
D. All of the above
Answer : D
3. Military type of organisation is known as
A. Line organisation
B. Functional organisation
C. Line and staff organisation
D. Line, staff and functional organisation
Answer : A
4. A big advantage of PERT over Gantt charts is that in the former case
A. Activities and events are clearly shown
B. Early start and late finish of an activity are clearly marked
C. Activity times are clear
D. Interrelationship among activities is clearly shown.
Answer : D
5. In A-B-C analysis, which class of items are generally large in number?
A. A
B. B
C. C
D. None of these
Answer : C
6. Routing prescribes the
A. Flow of material in the plant
B. Proper utilization of man power
C. Proper utilization of machines
D. Inspection of final product
Answer : A
7. Under the Apprenticeship Act
A. All industries have to necessarily train the apprentices
B. Industries have to train apprentices according to their requirement
C. All industries employing more than 100 workers have to recruit apprentices
D. Only industries employing more than 500 workers have to recruit apprentices
Answer : D
8. CPM is the
A. Time oriented technique
B. Event oriented technique
C. Activity oriented technique
D. Target oriented technique
Answer : C
9. Direct expenses include
A. Factory expenses
B. Selling expenses
C. Administrative expenses
D. None of these
Answer : D
10. Job evaluation is the method of determining the
A. Relative worth of jobs
B. Skills required by a worker
C. Contribution of a worker
D. Contribution of a job
Answer : A
11. Pick up the correct statement about relationship between various floats
A. Free float = total float
B. Independent float = total float
C. Independent float > free float
D. Independent float < free float
Answer : D
12. The grouping of activities into organisational units is called
A. Corporate plans
B. Higher level management
C. Functional authority
D. Departmentation
Answer : D
13. CPM stands for
A. Combined Process Method
B. Critical Path Method
C. Common Planning Method
D. Critical Process Method
Answer : B
14. Father of time study was
A. F.W. Taylor
B. H.L. Gantt
C. F.B. Gilbert
D. R.M. Barnes
Answer : A
15. A diagram showing the path followed by men and materials while performing a task is known as
A. String diagram
B. Flow process chart
C. Travel chart
D. Flow diagram
Answer : D
16. Dummy activities are used to
A. Determine the critical path
B. Determine the project completion time
C. Maintain the required net work
D. None of these
Answer : C
17. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
A. One-fourth
B. One-half
C. Equal to
D. Twice
Answer : B
18. According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Answer : A
19. The technique for establishing and maintaining priorities among the various jobs of any project is known as
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
Answer : B
20. The simplex method is the basic method for
A. Value analysis
B. Operation research
C. Linear programming
D. Model analysis
Answer : C
21. Breakeven analysis is a
A. Short term analysis
B. Long term analysis
C. Average of short and long term analysis
D. Any one of these
Answer : A
22. Which one of the following chart gives simultaneously information about the progress of work and machine loading?
A. Process chart
B. Machine load chart
C. Man-machine chart
D. Gantt chart
Answer : C
23. In the Halsey 50-50 plan, the following are rewarded more
A. Past good workers
B. Past poor workers
C. Past average workers
D. All of the above
Answer : B
24. Basic tool in work study is
A. Graph paper
B. Process chart
C. Planning chart
D. Stop watch
Answer : D
25. A-B-C analysis is used in
A. CPM
B. PERT
C. Inventory control
D. All of these
Answer : C
26. Activity slack or float of any event on a PERT/CPM chart is represented by
A. Latest start time of succeeding event earliest finish time of preceding event activity time
B. Latest start time of the event earliest start time of the event
C. Latest finish time of event earliest finish time of the event
D. Anyone of the above
Answer : D
27. PERT requires
A. Single time estimate
B. Double time estimate
C. Triple time estimate
D. None of these
Answer : C
28. The most important function of inventory control is
A. Stock control system
B. To run the stores effectively
C. Technical responsibility for the state of materials
D. All of the above
Answer : D
29. In time study, the rating factor is applied to determine
A. Standard time of a job
B. Merit rating of the worker
C. Fixation of incentive rate
D. Normal time of a worker
Answer : C
30. The important file in making a PERT is
A. An event can't be accomplished until activities leading to it are completed
B. No activity from any event can be started from preceding event till it is completed
C. Length of arrow has nothing to do with time
D. All of the above
Answer : D
31. PERT is the
A. Time oriented technique
B. Event oriented technique
C. Activity oriented technique
D. Target oriented technique
Answer : B
32. The production cost per unit can be reduced by
A. Producing more with increased inputs
B. Producing more with the same inputs
C. Eliminating idle time
D. Minimising resource waste
Answer : B
33. A milestone chart
A. Shows the inter dependences of various jobs
B. Depicts the delay of jobs, if any
C. Points outgoing ahead of schedule of jobs, if any
D. None of the above
Answer : D
34. The assumption in PERT is
A. A project will always be behind schedule, if left uncorrected
B. Cost of project will always be more than the estimated cost, if no timely corrections are taken
C. A project can be subdivided into a set of predictable, independent activities
D. Activities are fixed and can't be changed
Answer : C
35. Which of the following layouts is suited to job production?
A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer : A
36. The chart which gives an estimate about the amount of materials handling between various work stations is known as
A. Flow chart
B. Process chart
C. Travel chart
D. Operation chart
Answer : C
37. ABC analysis deals with
A. Analysis of process chart
B. Flow of material
C. Ordering schedule of job
D. Controlling inventory costs money
Answer : D
38. In which of the following layouts, the lines need to the balanced
A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer : B
39. Emergency rush order can be pushed more effectively in
A. Job production
B. Automatic production
C. Continuous production
D. Intermittent production
Answer : D
40. In value engineering, important consideration is given to
A. Customer satisfaction
B. Function concept
C. Profit maximisation
D. Cost reduction
Answer : D
41. What does symbol 'O' imply in work study?
A. Operation
B. Inspection
C. Transport
D. Delay/temporary storage
Answer : A
42. Breakeven analysis consists of
A. Fixed cost
B. Variable cost
C. Fixed and variable costs
D. Operation costs
Answer : C
43. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
A. 0.50
B. 0.66
C. 0.84
D. 0.95
Answer : C
44. The main advantage of line organisation is its
A. Effective command and control
B. Defined responsibilities at all levels
C. Rigid discipline in the organisation
D. All of the above
Answer : D
45. In manufacturing management, the term 'Dispatching' is used to describe
A. Dispatch of sales order
B. Dispatch of factory mail
C. Dispatch of finished product of the user
D. Dispatch of work orders through shop floor
Answer : D
46. Process layout is employed for
A. Batch production
B. Continuous type of product
C. Effective utilisation of machines
D. All of the above
Answer : A
47. For a product layout the material handling equipment must
A. Have full flexibility
B. Employ conveyor belts, trucks, tractors etc.
C. Be a general purpose type
D. Be designed as special purpose for a particular application
Answer : D
48. Which of the following plans motivates supervisors by paying a premium on time saved by workers?
A. Halsey plan
B. Rowan plan
C. Haynes plan
D. Emerson's plan
Answer : C
49. A critical activity has
A. Maximum slack
B. Minimum slack
C. Zero slack
D. Average slack
Answer : C
50. Critical Path Net Work helps an engineer
A. To concentrate his attention on critical activities
B. To divert the resources from noncritical advanced activities to critical activities
C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. All of the above
Answer : D