Construction Planning and Management 1000+ MCQ with answer for RBI Assistant

Thursday 9th of March 2023

Sharing is caring

1. Sinking fund is
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
Answer : A
2. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
A. Ice
B. Concrete
C. Loose sand
D. Earth
Answer : D
3. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
Answer : A
4. CPM is
A. Synthesising in concepts
B. Is built of activities oriented programme
C. Is based on time estimate
D. All the above
Answer : D
5. Critical path
A. Is always longest
B. Is always shortest
C. May be longest
D. May be shortest
Answer : A
6. The critical activity has
A. Maximum float
B. Minimum float
C. Zero float
D. None of these
Answer : C
7. A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
C. Does not consume time
D. All the above
Answer : D
8. For completion of a project, the critical path of the network represents
A. Minimum time
B. Maximum time
C. Maximum cost
D. Minimum cost
Answer : A
9. Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct
B. 1 and 4 are correct
C. 2, 3 and 4 are correct
D. 1, 2 and 4 are correct
Answer : B
10. Which of the following does not represent an activity?
A. Site located
B. Foundation is being dug
C. The office area is being cleaned
D. The invitations are being sent
Answer : A
11. Select the incorrect statement.
A. Start float and finish float are always equal.
B. Total float can be either start float or finish float.
C. Start float and finish float need not be equal.
D. Start float and finish float are the differences between activity times and not event times.
Answer : C
12. The estimated time required to perform an activity, is known as
A. Event
B. Dummy
C. Duration
D. Float
Answer : C
13. Free float for any activity is defined as the difference between
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
Answer : A
14. Pick up the correct statement from the following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. In CPM, the time is related to cost
D. All the above
Answer : D
15. Interfering float is the difference between
A. Total float and free float
B. Total float and independent float
C. Free float and independent float
D. None of the above
Answer : A
16. The direct cost of a project with respect to normal time is
A. Minimum
B. Maximum
C. Zero
D. Infinite
Answer : A
17. The reduction in project time normally results in
A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
Answer : B
18. Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Of these statement

A. (i) and (iii) are correct
B. (i) and (iv) are correct
C. (ii) and (iii) are correct
D. (ii) and (iv) are correct
Answer : B
19. A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects
B. Could invest in either of the two projects
C. Should invest in project A
D. Should invest in project B
Answer : A
20. For a given size of bucket, the ideal output of a dragline will be least in
A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay
Answer : D
21. Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5
B. 1, 3, 2, 4, 5
C. 1, 2, 3, 4, 5
D. 1, 3, 4, 2, 5
Answer : C
22. Consider the following statements: Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control. Of these statements

A. 1, 3 and 4 are correct
B. 2, 3 and 4 are correct
C. 1, 2 and 3 are correct
D. 1, 2 and 4 are correct
Answer : C
23. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
A. (a + m + b)/6
B. (a + 2m + b)/6
C. (a + 4m + b)/6
D. (a + 5m + b)/6
Answer : C
24. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A. 8 days
B. 9 days
C. 10 days
D. 15 days
Answer : B
25. The salient feature of functional organisation is
A. Strict adherence to specifications
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All the above
Answer : D
26. Economic saving of time results by crashing
A. Cheapest critical activity
B. Cheapest noncritical activity
C. Costliest critical activity
D. Costliest noncritical activity
Answer : A
27. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
Answer : D
28. Pick up the correct statement from the following:
A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
C. The difference between total float and free float, is called interfering float
D. All the above
Answer : D
29. Pick up the PERT event from the following:
A. Digging of foundation started
B. Digging of foundation completed
C. Laying of concrete started
D. All the above
Answer : D
30. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
A. (t1 - t2) - t
B. t - (t1 - t2)
C. (t1 + t2) - t
D. t + (t1 - t2)
Answer : A
31. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
A. 20 kg/tonne
B. 30 kg/tonne
C. 40 kg/tonne
D. 50 kg/tonne
Answer : C
32. The object of technical planning, is
A. Preparation of specifications
B. Preparation of estimates
C. Initiating the procurement action of resources
D. All the above
Answer : D
33. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
A. Event
B. Free float
C. Dummy
D. Constraint
Answer : C
34. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer : C
35. Preliminary project report for a road project must contain
A. The detailed estimated cost based on detailed design
B. The several alternatives of the project that have been considered
C. The soil survey, traffic survey, concept design and approximate cost
D. The contract documents for inviting tenders
Answer : C
36. The time with which direct cost does not reduce with the increase in time is known as
A. Crash time
B. Normal time
C. Optimistic time
D. Standard time
Answer : B
37. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Assistant Engineer
Answer : B
38. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
A. Only (i) is correct
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
Answer : C
39. In the given figure, the network of a project represents

A. Activity of an excavation of a footing
B. Activity of an excavation which starts at event No. 1 and ends at even No. 2
C. Activity of excavation which takes 8 units of time
D. None of these
Answer : C
40. Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
Answer : B
41. Critical path method
A. Is an improvement upon bar chart method
B. Provides a realistic approach to daily problems
C. Avoids delays which are very common in bar charts
D. All the above
Answer : D
42. A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
A. 3.7 years
B. 4.23 years
C. 5 years
D. 7.87 years
Answer : B
43. For excavating utility trenches with precise control of depth, the excavation equipment used is
A. Hoe
B. Shovel
C. Dragline
D. None of the above
Answer : A
44. If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
A. Equal to X
B. More than X
C. Less than X
D. Any of the above
Answer : C
45. Batching refers to
A. Controlling the total quantity at each batch
B. Weighing accurately, the quantity of each material for a job before mixing
C. Controlling the quantity of each material into each batch
D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Answer : C
46. The basic action involved in sheep foot rolling is
A. Kneading
B. Pressing
C. Tamping
D. Vibration
Answer : A
47. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A. Total float
B. Free float
C. Interfering float
D. Independent float
Answer : D
48. The time which results in the leasi, possible construction cost of an activity, is known as
A. Normal time
B. Slow time
C. Crash time
D. Standard time
Answer : B
49. The most popular type of organisation used for Civil Engineering Constructions, is
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : A
50. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

A. 19
B. 14
C. 24
D. None of these
Answer : A