Construction Planning and Management MCQ Solved Paper for RRB JE

Thursday 9th of March 2023

Sharing is caring

1. Time and progress chart of a construction, is also known as
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. All the above
Answer : D
2. The independent float affects only
A. Preceding activities
B. Succeeding activities
C. The particular activity involved
D. None of the above
Answer : C
3. For completion of a project, the critical path of the network represents
A. Minimum time
B. Maximum time
C. Maximum cost
D. Minimum cost
Answer : A
4. A CPM family includes
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. All the above
Answer : D
5. Henry Gantt developed Bar charts for planning and scheduling of projects in
A. 1880
B. 1900
C. 1920
D. 1940
Answer : B
6. Military organisation is known as
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. None of these
Answer : A
7. Earliest finish of an activity is always
A. Greater than earliest event time of the following node
B. Less than earliest event time of the following node
C. Less than or equal to earliest event time of the following node
D. Greater than or equal to earliest event time of the following node
Answer : C
8. In the given figure, the network of a project represents

A. Activity of an excavation of a footing
B. Activity of an excavation which starts at event No. 1 and ends at even No. 2
C. Activity of excavation which takes 8 units of time
D. None of these
Answer : C
9. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
Answer : A
10. The final selection of a construction site, is done by
A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
D. All the above
Answer : D
11. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer : C
12. In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
A. Yes, because of heavier overheads and handling cost
B. Yes, because of the very high order of quality control for the factory made components
C. No, because of repetitive manufacture of a number of elements
D. No, because of savings in site labour
Answer : C
13. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
A. 80 and 90
B. 90 and 80
C. 85 and 75
D. 75 and 83
Answer : D
14. Pick up the correct statement from the following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. In CPM, the time is related to cost
D. All the above
Answer : D
15. Pick up the correct statement from the following:
A. Earliest expected time is denoted by TE
B. Latest occurrence time is denoted by TL
C. Contractual obligation time is denoted by Ts
D. All the above
Answer : D
16. At a work site, statistical quality control of concrete means
A. Measurement of risks to eliminate failures
B. Applying the theory' of probability to sample testing or inspection
C. Reduction in wastage of inspection costs
D. Reduction in costs for the removal of defects
Answer : B
17. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
A. 1
B. 2
C. 3
D. 4
Answer : A
18. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
A. to + 3tm+ tp/3
B. to + 4tm+ tp/4
C. to + 4tm+ tp/5
D. to + 4tm+ tp/6
Answer : D
19. Updating may result in
A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
D. All of the above
Answer : D
20. Free float for any activity is defined as the difference between
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
Answer : A
21. Frequency distribution curves
A. Having a single lump, are called uninodal curves
B. If symmetrical, are called normal curves
C. If not symmetrical, are called skew curves
D. All the above
Answer : D
22. Pick up the incorrect statement from the following:
A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
B. The difference between the maximum time available for the job and actual time it consumes, is called total float
C. The difference between the latest start time and earliest start time of an activity, is called total float
D. None of these
Answer : D
23. The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
A. 3425 kg
B. 5515 kg
C. 4350 kg
D. 2975 kg
Answer : B
24. PERT analysis is based on
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All the above
Answer : D
25. Which of the following excavators is most suitable for digging under water?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Answer : A
26. The probability of completion of any activity within its expected time is
A. 50 %
B. 84.1 %
C. 99.9 %
D. 100 %
Answer : A
27. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
Answer : A
28. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
Answer : D
29. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A. Total float
B. Free float
C. Interfering float
D. Independent float
Answer : D
30. Which one of the following represents an activity?
A. Excavation for foundation
B. Curing of concrete
C. Setting of question paper
D. All the above
Answer : D
31. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
A. Duration
B. Total float
C. Free float
D. Interfering float
Answer : C
32. For excavating utility trenches with precise control of depth, the excavation equipment used is
A. Hoe
B. Shovel
C. Dragline
D. None of the above
Answer : A
33. Pick up the correct statement from the following:
A. The difference of latest occurrence time and earliest expected time, is called slack
B. The activities connecting the events having zero slack, lie on the critical path
C. The critical path consumes the maximum time
D. All the above
Answer : D
34. The main principle of an organisation, is
A. Unity of command
B. Effective control at all levels
C. Delegation of authority
D. All the above
Answer : D
35. Power stations are generally treated as
A. Light construction
B. Heavy construction
C. Industrial construction
D. Electrical construction
Answer : C
36. While scheduling a project by C.P.M.
A. A project is divided into various activities
B. Required time for each activity is established
C. Net work is drawn by connecting the activities and the events
D. All the above
Answer : D
37. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
A. 4 days
B. 6 days
C. 10 days
D. 16 days
Answer : D
38. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

A. 20
B. 25
C. 35
D. 15
Answer : B
39. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
40. The technique for establishing and maintaining priorities among the various jobs of a project, is known
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
Answer : B
41. Site order book is used for recording
A. Instructions by the executive engineers
B. Construction measurements
C. Issue of store equipments
D. Names of the casual labour
Answer : A
42. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
A. LST-EST
B. LFT-EFT
C. TL-EFT
D. All the above
Answer : D
43. Total float for any activity is defined as the difference between
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
Answer : B
44. The critical activity has
A. Maximum float
B. Minimum float
C. Zero float
D. None of these
Answer : C
45. The salient feature of functional organisation is
A. Strict adherence to specifications
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All the above
Answer : D
46. Select the incorrect statement.
A. A critical path always begins at the very first event.
B. A critical path always terminates at the last event.
C. Critical activities control the project duration.
D. Critical activity is the one for which free float is zero.
Answer : D
47. The time corresponding to minimum total project cost is
A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
Answer : D
48. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
A. 3.5 and 5/6
B. 5 and 25/36
C. 3.5 and 25/36
D. 4 and 5/6
Answer : C
49. In resources levelling
A. Total duration of project is reduced
B. Total duration of project is increased
C. Uniform demand of resources is achieved
D. Cost of project is controlled
Answer : C
50. A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
A. 3.7 years
B. 4.23 years
C. 5 years
D. 7.87 years
Answer : B