1. Dummy activities are used to
A. Determine the critical path
B. Determine the project completion time
C. Maintain the required net work
D. None of these
Answer : C
2. Valve analysis is particularly of interest when
A. Jobbing work economics are involved
B. Production is on large scale
C. Only few components are involved
D. Costly equipment is used
Answer : B
3. A feasible solution to the linear programming problem should
A. Satisfy the problem constraints
B. Optimise the objective function
C. Satisfy the problem constraints and non-negativity restrictions
D. Satisfy the non-negativity restrictions
Answer : C
4. Time study is used to
A. Determine standard costs
B. Determine the number of machines a person may run
C. Provide a basis for setting piece price or incentive wages
D. All of the above
Answer : D
5. Work study is done with the help of
A. Process chart
B. Material handling
C. Stop watch
D. All of the above
Answer : C
6. In manufacturing management, the term 'Dispatching' is used to describe
A. Dispatch of sales order
B. Dispatch of factory mail
C. Dispatch of finished product of the user
D. Dispatch of work orders through shop floor
Answer : D
7. An activity of the project is graphically represented by ________ on the network diagram.
A. A circle
B. A straight line
C. An arrow
D. None of these
Answer : C
8. Standard time is defined as
A. Normal time + allowances
B. Normal time + idle time + allowances
C. Normal time + idle time
D. Only normal time for an operation
Answer : A
9. In inventory control, the economic order quantity is the
A. Optimum lot size
B. Highest level of inventory
C. Lot corresponding to breakeven point
D. Capability of a plant to produce
Answer : A
10. The performance of a specific task in CPM is known as
A. Dummy
B. Event
C. Activity
D. Contract
Answer : C
11. The difference between the time available to do the job and the time required to do the job, is known as
A. Event
B. Float
C. Duration
D. Constraint
Answer : B
12. Direct expenses include
A. Factory expenses
B. Selling expenses
C. Administrative expenses
D. None of these
Answer : D
13. Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?
A. Emerson efficiency plan
B. Taylor plan
C. Halsey premium plan
D. Gilbert plan
Answer : C
14. Process layout is also known as
A. Analytical-layout
B. Synthetic layout
C. Static product layout
D. None of these
Answer : A
15. In fixed position layout
A. Total production cost is less
B. Material movement is less
C. Capital investment is minimum
D. All of these
Answer : D
16. CPM stands for
A. Combined Process Method
B. Critical Path Method
C. Common Planning Method
D. Critical Process Method
Answer : B
17. Breakeven analysis consists of
A. Fixed cost
B. Variable cost
C. Fixed and variable costs
D. Operation costs
Answer : C
18. PERT/CPM, techniques can be used for following applications
A. Once through project
B. Maintenance jobs
C. Research and development
D. All of the above
Answer : D
19. The mathematical technique for finding the best use of limited resources in an optimum manner is known as
A. Operation research
B. Linear programming
C. Network analysis
D. Breakeven analysis
Answer : B
20. The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as
A. Job enlargement
B. Job enrichment
C. Job rotation
D. Job evaluation
Answer : B
21. Positive slack on a PERT indicates that project is
A. Ahead of schedule
B. Beyond schedule
C. As per schedule
D. On critical path
Answer : A
22. In break even analysis, total cost consists of
A. Fixed cost + sales revenue
B. Variable cost + sales revenue
C. Fixed cost + variable cost
D. Fixed cost + variable cost + profit
Answer : C
23. Pick up the incorrect statement about advantages of work sampling
A. Permits a fine breakdown of activities and delays
B. Simultaneous study of many operators may be made by a single observer
C. Calculations are easier, method is economical and less time consuming
D. No time measuring devices are generally needed
Answer : A
24. Micro-motion study involves following number of fundamental hand motions
A. 8
B. 12
C. 16
D. 20
Answer : C
25. Indirect expenses include
A. Factory expenses
B. Selling expenses
C. Administrative expenses
D. All of these
Answer : D
26. Pick up the correct statement about relationship between various floats
A. Free float = total float
B. Independent float = total float
C. Independent float > free float
D. Independent float < free float
Answer : D
27. Value engineering aims at finding out the
A. Depreciation value of a product
B. Resale value of a product
C. Major function of the item and accomplishing the same at least cost without change in quality
D. Breakeven point when machine requires change
Answer : C
28. Which of the following is not wage incentive plan?
A. Differential piece rate system
B. Rowan plan
C. Emerson plan
D. Taylor plan
Answer : D
29. The purpose of micro-motion study is to
A. Assist in finding out the most efficient way of doing work
B. Train the individual operator regarding the motion economy principles
C. Help in collecting the motion time data for synthetic time standards
D. All of the above
Answer : D
30. Which of the following plans motivates supervisors by paying a premium on time saved by workers?
A. Halsey plan
B. Rowan plan
C. Haynes plan
D. Emerson's plan
Answer : C
31. The reasons which are basically responsible for the formation of a queue should be that
A. The average service rate Hess than the average arrival rate
B. Output rate is linearly proportional to input
C. Output rate is constant and the input varies in a random manner
D. All of the above
Answer : D
32. Motion study involves analysis of
A. Actions of operator
B. Layout of work place
C. Tooling and equipment
D. All of the above
Answer : A
33. Under the Apprenticeship Act
A. All industries have to necessarily train the apprentices
B. Industries have to train apprentices according to their requirement
C. All industries employing more than 100 workers have to recruit apprentices
D. Only industries employing more than 500 workers have to recruit apprentices
Answer : D
34. A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called
A. Hoist
B. Jib crane
C. Portable elevator
D. Chain conveyor
Answer : A
35. The salient feature of functional organisation is
A. Strict adherence to specification
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All of the above
Answer : D
36. For material transportation, conveyors are used when the prevailing conditions include
A. Loads are uniform
B. Routes do not vary
C. Materials move relatively continuously
D. All of these
Answer : D
37. Which of the following are the principles of material handling?
A. Keep all the handling to the minimum
B. Select only efficient handling equipment
C. Move the heaviest weight to the least distance
D. All of the above
Answer : D
38. Replacement studies are made on the following basis:
A. Annual cost method
B. Rate of return method
C. Total life average method
D. Any one of the above
Answer : D
39. According to Rowan plan of wage incentive system, bonus is paid to a worker
A. Whose output exceeds 67% efficiency
B. On the percentage of time saved
C. On the percentage of time worked
D. On the percentage of standard time
Answer : C
40. Graphical method, simplex method, and transportation method are concerned with
A. Breakeven analysis
B. Value analysis
C. Linear programming
D. Queueing theory
Answer : C
41. A graphical device used to determine the breakeven point and profit potential under varying conditions of output and costs, is known as
A. Gantt chart
B. Flow chart
C. Breakeven chart
D. PERT chart
Answer : C
42. ABC analysis deals with
A. Analysis of process chart
B. Flow of material
C. Ordering schedule of job
D. Controlling inventory costs money
Answer : D
43. The deductions for, employees provident fund start
A. Immediately on joining the service
B. After 60 days of joining the service
C. After 100 days of joining the service
D. After 240 days of joining the service
Answer : D
44. Bin card is used in
A. Administrative wing
B. Workshop
C. Foundry shop
D. Stores
Answer : D
45. Linear programming can be applied successfully to
A. Chemical industry
B. Oil industry
C. Banks
D. All of these
Answer : D
46. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
A. 0.50
B. 0.66
C. 0.84
D. 0.95
Answer : C
47. The linear programming techniques can be applied successfully to industries like
A. Iron and steel
B. Food processing
C. Oil and chemical
D. All of the above
Answer : D
48. Current assets include
A. Manufacturing plant
B. Manufacturing plant and equipment
C. Inventories
D. Common stock held by the firm
Answer : A
49. The value engineering technique in which experts of the same rank assemble for product development is called
A. Delphi
B. Brain storming
C. Morphological analysis
D. Direct expert comparison
Answer : B
50. Pick up the correct statement from the following
A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed
B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
D. All of the above
Answer : D