1. The reasons which are basically responsible for the formation of a queue should be that
A. The average service rate Hess than the average arrival rate
B. Output rate is linearly proportional to input
C. Output rate is constant and the input varies in a random manner
D. All of the above
Answer : D
2. Work sampling is applied for
A. Estimation of the percentage utilisation of machine tools
B. Estimating the percentage of the time consumed by various job activities
C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
D. All of the above
Answer : D
3. In a functional organisation
A. Quality of work is better
B. Wastage of material is minimum
C. Specialised knowledge and guidance to individual worker is provided
D. All of the above
Answer : D
4. Job evaluation is the method of determining the
A. Relative worth of jobs
B. Skills required by a worker
C. Contribution of a worker
D. Contribution of a job
Answer : A
5. Pick up the correct statement about relationship between various floats
A. Free float = total float
B. Independent float = total float
C. Independent float > free float
D. Independent float < free float
Answer : D
6. CPM is the
A. Time oriented technique
B. Event oriented technique
C. Activity oriented technique
D. Target oriented technique
Answer : C
7. Tick the odd man out
A. Taylor
B. Drucker
C. McGregor
D. Galileo
Answer : D
8. Pessimistic time is
A. The maximum time which an activity might require
B. The average time required for a job
C. The most probable time considering all conditions
D. The minimum time in which an activity can possibly be accomplished
Answer : A
9. In the Halsey system of wage incentive plan, a worker is
A. Paid as per efficiency
B. Ensured of minimum wages
C. Not paid any bonus till his efficiency
D. Never a loser
Answer : B
10. Merit Rating is the method of determining worth of
A. A job
B. An individual employee
C. A particular division in workshop
D. Machine
Answer : B
11. Which of the following statement is correct?
A. A-B-C analysis is based on Pareto's principle
B. Simulation can be used for inventory control
C. Economic order quantity formula ignores variations in demand pattern
D. All of the above
Answer : A
12. Breakeven analysis consists of
A. Fixed cost
B. Variable cost
C. Fixed and variable costs
D. Operation costs
Answer : C
13. The start or completion of task is called
A. An event
B. An activity
C. A duration
D. None of these
Answer : A
14. In value engineering, important consideration is given to
A. Customer satisfaction
B. Function concept
C. Profit maximisation
D. Cost reduction
Answer : D
15. Choose the wrong statement. Motion study is used for
A. Improving a work method
B. Improvising a work method
C. Designing a work method
D. Reducing inventory costs
Answer : D
16. A critical activity has
A. Maximum slack
B. Minimum slack
C. Zero slack
D. Average slack
Answer : C
17. Direct expenses include
A. Factory expenses
B. Selling expenses
C. Administrative expenses
D. None of these
Answer : D
18. If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then breakeven point is equal to
A. (F × V)/P
B. (F × P)/V
C. F/[1 + (V/P)]
D. F/[1 - (V/P)]
Answer : D
19. Acceptance sampling is used in
A. Job production
B. Batch production
C. Mass production
D. All of these
Answer : C
20. Indirect expenses include
A. Factory expenses
B. Selling expenses
C. Administrative expenses
D. All of these
Answer : D
21. Gantt chart gives information about
A. Scheduling and routing
B. Sales
C. Production schedule
D. Machine utilisation
Answer : C
22. The mathematical technique for finding the best use of limited resources in an optimum manner is known as
A. Operation research
B. Linear programming
C. Network analysis
D. Breakeven analysis
Answer : B
3. The objective of time study is to determine the time required to complete a job by
A. Fast worker
B. Average worker
C. Slow worker
D. New entrant
Answer : B
24. A-B-C analysis is used in
A. CPM
B. PERT
C. Inventory control
D. All of these
Answer : C
25. The critical path of a network represents
A. The minimum time required for completion of project
B. The maximum time required for completion of project
C. Maximum cost required for completion of project
D. Minimum cost required for completion of project
Answer : A
26. The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
A. Event
B. Free float
C. Artificial
D. Dummy
Answer : D
27. Slack represents the difference between the
A. Latest allowable time and the normal expected time
B. Latest allowable time and the earliest expected time
C. Proposed allowable time and the earliest expected time
D. Normal allowable time and the latest expected time
Answer : B
28. The time taken by a trained worker to perform an operation, while working a steady pace, is known as
A. Standard time
B. Normal time
C. Representative time
D. None of these
Answer : A
29. The important file in making a PERT is
A. An event can't be accomplished until activities leading to it are completed
B. No activity from any event can be started from preceding event till it is completed
C. Length of arrow has nothing to do with time
D. All of the above
Answer : D
30. Expediting function consists in keeping a watch on
A. Operator's activity
B. Flow of material and in case of trouble locate source of trouble
C. Minimising the delays
D. Making efficient despatching
Answer : B
31. The type of layout used for manufacturing steam turbines, is
A. Product layout
B. Process layout
C. Fixed position layout
D. Any one of these
Answer : C
32. Routing prescribes the
A. Flow of material in the plant
B. Proper utilization of man power
C. Proper utilization of machines
D. Inspection of final product
Answer : A
33. Service time in queuing theory is usually assumed to follow
A. Normal distribution
B. Poissons distribution
C. Erlang distribution
D. Exponential law
Answer : D
34. The most suitable incentive plan for the maintenance section of an industry will be
A. Piece rate system
B. Group incentive plan
C. Profit sharing plans
D. Simplification
Answer : B
35. In a line organisation
A. Responsibility of each individual is fixed
B. Discipline is strong
C. Quick decisions are taken
D. All of these
Answer : D
36. Standing orders which are statutory are applicable to
A. All industries
B. All process industries and thermal power plants
C. Only major industries
D. All industries employing more than 100 workers
Answer : D
37. Acceptance sampling is widely used in
A. Batch production
B. Job production
C. Mass production
D. All of the above
Answer : C
38. Bin card is used in
A. Administrative wing
B. Workshop
C. Foundry shop
D. Stores
Answer : D
39. In inventory control, the economic order quantity is the
A. Optimum lot size
B. Highest level of inventory
C. Lot corresponding to breakeven point
D. Capability of a plant to produce
Answer : A
40. The salient feature of functional organisation is
A. Strict adherence to specification
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All of the above
Answer : D
41. A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called
A. Hoist
B. Jib crane
C. Portable elevator
D. Chain conveyor
Answer : A
42. The most popular type of organisation used for Civil Engineering Constructions is
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : A
43. Product layout is used for
A. Job production
B. Batch production
C. Mass production
D. Any one of these
Answer : C
44. Pick up the correct statement from the following
A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed
B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
D.All of the above
Answer : D
45. Under the Apprenticeship Act
A. All industries have to necessarily train the apprentices
B. Industries have to train apprentices according to their requirement
C. All industries employing more than 100 workers have to recruit apprentices
D. Only industries employing more than 500 workers have to recruit apprentices
Answer : D
46. The deductions for, employees provident fund start
A. Immediately on joining the service
B. After 60 days of joining the service
C. After 100 days of joining the service
D. After 240 days of joining the service
Answer : D
47. If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
A. EF = ES + D
B. LS = LFD
C. LF = LS + D
D. All of the above
Answer : D
48. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
A. Latest start time earliest start time
B. Latest finish time earliest finish time (EFT)
C. TLEFT
D. All of the above
Answer : D
49. The main objective of work measurement is to
A. Plan and schedule of production
B. Formulate a proper incentive scheme
C. Estimate the selling prices and delivery dates
D. All of the above
Answer : D
50. The grouping of activities into organisational units is called
A. Corporate plans
B. Higher level management
C. Functional authority
D. Departmentation
Answer : D