1. The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as
A. Duration
B. Total float
C. Free float
D. Interfering float
Answer : C
2. Which of the following organisation is preferred in automobile industry?
A. Functional organisation
B. Line organisation
C. Staff organisation
D. Line and staff organisations
Answer : D
3. Which one of the following represents a group incentive plan?
A. Scanlon Plan
B. Rowan Plan
C. Taylor Differential Piece Rate System
D. Halsey Premium Plan
Answer : A
4. For a product layout the material handling equipment must
A. Have full flexibility
B. Employ conveyor belts, trucks, tractors etc.
C. Be a general purpose type
D. Be designed as special purpose for a particular application
Answer : D
5. Merit Rating is the method of determining worth of
A. A job
B. An individual employee
C. A particular division in workshop
D. Machine
Answer : B
6. Routing is essential in the following type of industry
A. Assembly industry
B. Process industry
C. Job order industry
D. Mass production industry
Answer : A
7. In the Halsey system of wage incentive plan, a worker is
A. Paid as per efficiency
B. Ensured of minimum wages
C. Not paid any bonus till his efficiency
D. Never a loser
Answer : B
8. Gantt chart gives information about
A. Scheduling and routing
B. Sales
C. Production schedule
D. Machine utilisation
Answer : C
9. CPM stands for
A. Combined Process Method
B. Critical Path Method
C. Common Planning Method
D. Critical Process Method
Answer : B
10. The simplex method is the basic method for
A. Value analysis
B. Operation research
C. Linear programming
D. Model analysis
Answer : C
11. At the breakeven point,
A. Total cost is more than the sales revenue
B. Total cost is less than the sales revenue
C. Total cost is equal to sales revenue
D. Fixed cost is equal to variable cost
Answer : C
12. In break even analysis, total cost consists of
A. Fixed cost + sales revenue
B. Variable cost + sales revenue
C. Fixed cost + variable cost
D. Fixed cost + variable cost + profit
Answer : C
13. The mathematical technique for finding the best use of limited resources in an optimum manner is known as
A. Operation research
B. Linear programming
C. Network analysis
D. Breakeven analysis
Answer : B
14. Abbreviated work factor data is applied for
A. Material handling operation
B. Maintenance operation
C. Packing and shipping operation
D. All of these
Answer : D
15. Product layout is also known as
A. Analytical layout
B. Synthetic layout
C. Static product layout
D. None of these
Answer : B
16. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker
A. Whose output exceeds 67% efficiency
B. On the percentage of time saved
C. On the percentage of time worked
D. On the percentage of standard time
Answer : A
17. Slack represents the difference between the
A. Latest allowable time and the normal expected time
B. Latest allowable time and the earliest expected time
C. Proposed allowable time and the earliest expected time
D. Normal allowable time and the latest expected time
Answer : B
18. Critical path on PERT/CPM chart is obtained by joining the events having
A. Maximum slack
B. Minimum slack
C. Average slack
D. No slack
Answer : B
19. CPM is the
A. Time oriented technique
B. Event oriented technique
C. Activity oriented technique
D. Target oriented technique
Answer : C
20. A graphical device used to determine the breakeven point and profit potential under varying conditions of output and costs, is known as
A. Gantt chart
B. Flow chart
C. Breakeven chart
D. PERT chart
Answer : C
21. Line organisation is suitable for
A. Sugar industries
B. Oil refining industries
C. Spinning and weaving industries
D. All of these
Answer : D
22. Basic motion time study gives times for basic motions in ten thousandths of
A. Second
B. Minute
C. Hour
D. Day
Answer : B
23. PERT
A. Provides an approach for keeping planning up-to-date
B. Provides a way for management to require that planning be done on a uniform and logical basis
C. Permits management to foresee quickly the impact of variations from the plan
D. All of the above
Answer : D
24. Gantt charts are used for
A. Forecasting sales
B. Production schedule
C. Scheduling and routing
D. Linear programming
Answer : B
25. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
A. One-fourth
B. One-half
C. Equal to
D. Twice
Answer : B
26. Activity slack or float of any event on a PERT/CPM chart is represented by
A. Latest start time of succeeding event earliest finish time of preceding event activity time
B. Latest start time of the event earliest start time of the event
C. Latest finish time of event earliest finish time of the event
D. Anyone of the above
Answer : D
27. The main object of scientific layout is
A. To produce better quality of product
B. To utilise maximum floor area
C. To minimise production delays
D. All of these
Answer : D
28. The important file in making a PERT is
A. An event can't be accomplished until activities leading to it are completed
B. No activity from any event can be started from preceding event till it is completed
C. Length of arrow has nothing to do with time
D. All of the above
Answer : D
29. Expediting function consists in keeping a watch on
A. Operator's activity
B. Flow of material and in case of trouble locate source of trouble
C. Minimising the delays
D. Making efficient despatching
Answer : B
30. A low unit cost can be obtained by following
A. Product layout
B. Functional layout
C. Automatic material handling equipment
D. Specialisation of operation
Answer : A
31. Process layout is employed for
A. Batch production
B. Continuous type of product
C. Effective utilisation of machines
D. All of the above
Answer : A
32. Emergency rush order can be pushed more effectively in
A. Job production
B. Automatic production
C. Continuous production
D. Intermittent production
Answer : D
33. Micro-motion study is
A. Analysis of one stage of motion chart
B. Motion study, when seen on a time chart
C. Subdivision of an operation into therbligs and their analysis
D. Enlarged view of motion study
Answer : C
34. Routing prescribes the
A. Flow of material in the plant
B. Proper utilization of man power
C. Proper utilization of machines
D. Inspection of final product
Answer : A
35. Work study is most useful
A. Where production activities are involved
B. In judging the rating of machines
C. In improving industrial relations
D. In judging the output of a man and improving it
Answer : A
36. The basic difference between PERT and CPM is that
A. PERT deals with events and CPM with activities
B. Critical path is determined in PERT only
C. Costs are considered on CPM only and not in PERT
D. Guessed times are used in PERT and evaluated times in CPM
Answer : D
37. The work study is done by means of
A. Planning chart
B. Process chart
C. Stop watch
D. Any one of these
Answer : C
38. Scheduling
A. Prescribes the sequence of operations to be followed
B. Determines the programme for the operations
C. Is concerned with starting of processes
D. Regulates the progress of job through various processes
Answer : B
39. The probability distribution of activity times in PERT follows following distribution
A. Normal
B. Binomial
C. Beta
D. Exponential
Answer : C
40. Pick up the incorrect statement from the following. A critical ratio scheduling
A. Establishes the relative priorities among various activities on a common basis
B. Determines the status of each activity
C. Adjusts automatically changes in activity progress
D. None of the above
Answer : D
41. Work study comprises following main techniques
A. Method study and work measurement
B. Method study and time study
C. Time study and work measurement
D. Method study and job evaluation
Answer : A
42. Work sampling observations are taken on the basis of
A. Detailed calculations
B. Convenience
C. Table of random numbers
D. Past experience
Answer : C
43. Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is
A. 25
B. 50
C. 75
D. 100
Answer : B
44. In CPM, the cost slope is determined by
A. Crash cost/Normal Cost
B. (Crash Cost - Normal cost)/ (Normal time - Crash time)
C. Normal Cost/Crash cost
D. (Normal cost - Crash cost)/ (Normal time - Crash time)
Answer : B
45. The purpose of micro-motion study is to
A. Assist in finding out the most efficient way of doing work
B. Train the individual operator regarding the motion economy principles
C. Help in collecting the motion time data for synthetic time standards
D. All of the above
Answer : D
46. Value engineering aims at finding out the
A. Depreciation value of a product
B. Resale value of a product
C. Major function of the item and accomplishing the same at least cost without change in quality
D. Breakeven point when machine requires change
Answer : C
47. Merit rating is the method of determining the
A. Relative values of a job
B. Workers performance on a job
C. Worth of a machine
D. Value of overall production
Answer : B
48. Work study involves
A. Only method study
B. Only work measurement
C. Method study and work measurement
D. Only motion study
Answer : C
49. Which of the following is not wage incentive plan?
A. Differential piece rate system
B. Rowan plan
C. Emerson plan
D. Taylor plan
Answer : D
50. Discrepancies of bar chart techniques are
A. Consequential effects of lack in one activity on the finish date
B. Free time available for an activity can't be predicted
C. Effective monitoring/controlling can't be done
D. All of the above
Answer : D

Sharing is caring