1. PERT requires
A. Single time estimate
B. Double time estimate
C. Triple time estimate
D. None of these
Answer : C
2. The first method invented for planning projects was
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme evaluation and review technique (PERT)
Answer : A
3. Choose the wrong statement Time study is used to
A. Determine overhead expenses
B. Provide a basis for setting piece prices or incentive wages
C. Determine standard costs
D. Determine the capability of an operator to handle the number of machines
Answer : A
4. Service time in queuing theory is usually assumed to follow
A. Normal distribution
B. Poissons distribution
C. Erlang distribution
D. Exponential law
Answer : D
5. Line organisation is suitable for
A. Sugar industries
B. Oil refining industries
C. Spinning and weaving industries
D. All of these
Answer : D
6. Breakeven point is the point where
A. Fixed and variable cost lines intersect
B. Fixed and total cost lines intersect
C. Variable and total cost lines intersect
D. Sales revenue and total expensive lines intersect
Answer : D
7. Critical path moves along the activities having total float of
A. Positive value
B. Negative value
C. Zero value
D. Same value
Answer : C
8. Work study comprises following main techniques
A. Method study and work measurement
B. Method study and time study
C. Time study and work measurement
D. Method study and job evaluation
Answer : A
9. If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be
A. TR
B. TR + [(S - T)/2] × R
C. TR + (S - T) × R
D. TR + [(S - T)/S] × R
Answer : B
10. Activity slack or float of any event on a PERT/CPM chart is represented by
A. Latest start time of succeeding event earliest finish time of preceding event activity time
B. Latest start time of the event earliest start time of the event
C. Latest finish time of event earliest finish time of the event
D. Anyone of the above
Answer : D
11. In which of the following layouts, the lines need to the balanced
A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer : B
12. A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called
A. Hoist
B. Jib crane
C. Portable elevator
D. Chain conveyor
Answer : A
13. Which of the following is independent of sales forecast?
A. Productivity
B. Inventory control
C. Production planning
D. Production control
Answer : A
14. Pick up the incorrect statement about advantages of work sampling
A. Permits a fine breakdown of activities and delays
B. Simultaneous study of many operators may be made by a single observer
C. Calculations are easier, method is economical and less time consuming
D. No time measuring devices are generally needed
Answer : A
15. In Halsey 50-50 plan, output standards are established
A. By time study
B. From previous production records
C. From one's judgement
D. All of the above
Answer : B
16. The probability distribution of activity times in PERT follows following distribution
A. Normal
B. Binomial
C. Beta
D. Exponential
Answer : C
17. Product layout is best suited where
A. One type of product is produced
B. Product is standardised
C. Product is manufactured in large quantities
D. All of the above
Answer : D
18. F. W. Taylor introduced a system of organisation known as
A. Line organisation
B. Functional organisation
C. Line and staff organisation
D. Line, staff and functional organisation
Answer : B
19. The most popular type of organisation used for Civil Engineering Constructions is
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : A
20. Which of the following statement is correct about the network diagram?
A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.
B. The tail end of the arrow represents the start of an activity.
C. The head of the arrow represents the end of an activity.
D. All of the above
Answer : D
21. M.T.M. is used to
A. Improve existing methods
B. Establish time standards
C. Develop effective methods in advance of the beginning of production
D. All of the above
Answer : D
22. The technique for establishing and maintaining priorities among the various jobs of any project is known as
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
Answer : B
23. Which one of the following chart gives simultaneously information about the progress of work and machine loading?
A. Process chart
B. Machine load chart
C. Man-machine chart
D. Gantt chart
Answer : C
24. A milestone chart
A. Shows the inter dependences of various jobs
B. Depicts the delay of jobs, if any
C. Points outgoing ahead of schedule of jobs, if any
D. None of the above
Answer : D
25. Which of the following charts are used for plant layout design?
A. Operation process chart
B. Man machine chart
C. Travel chart
D. All of these
Answer : D
26. Templates are used for
A. A planning layout
B. Flow of material
C. Advancing a programme in automatic machines
D. Copying complicated profiles
Answer : A
27. CPM requires
A. Single time estimate
B. Double time estimate
C. Triple time estimate
D. None of these
Answer : A
28. Work sampling is applied for
A. Estimation of the percentage utilisation of machine tools
B. Estimating the percentage of the time consumed by various job activities
C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
D. All of the above
Answer : D
29. Direct expenses include
A. Factory expenses
B. Selling expenses
C. Administrative expenses
D. None of these
Answer : D
30. Which of the following equations is not in conformity with others?
A. Organisation performance × motivation = profits
B. Knowledge × skill = ability
C. Ability × motivation = performance
D. Attitude × situation = motivation
Answer : A
31. The type of organisation preferred for a steel industry, is
A. Line organisation
B. Functional organisation
C. Line and staff organisation
D. Line, staff and functional organisation
Answer : D
32. In ABC control policy, maximum attention is given to
A. Those items which consume money
B. Those items which are not readily available
C. Those × items which are in more demand
D. Those items which consume more money
Answer : D
33. Under the Apprenticeship Act
A. All industries have to necessarily train the apprentices
B. Industries have to train apprentices according to their requirement
C. All industries employing more than 100 workers have to recruit apprentices
D. Only industries employing more than 500 workers have to recruit apprentices
Answer : D
34. A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the
A. Fixed cost line
B. Variable cost line
C. Total cost line
D. Sales revenue line
Answer : B
35. Pick up the correct statement from the following
A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed
B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
D. All of the above
Answer : D
36. Current assets include
A. Manufacturing plant
B. Manufacturing plant and equipment
C. Inventories
D. Common stock held by the firm
Answer : A
37. Simplex method is the method used for
A. Value analysis
B. Network analysis
C. Linear programming
D. Queuing theory
Answer : C
38. The purpose of micro-motion study is to
A. Assist in finding out the most efficient way of doing work
B. Train the individual operator regarding the motion economy principles
C. Help in collecting the motion time data for synthetic time standards
D. All of the above
Answer : D
39. Earliest finish time can be regarded as
A. Earliest start time + duration of activity
B. Earliest start time duration of activity
C. Latest finish time + duration of activity
D. Latest finish time duration of activity
Answer : A
40. Which of the following statement is correct?
A. A-B-C analysis is based on Pareto's principle
B. Simulation can be used for inventory control
C. Economic order quantity formula ignores variations in demand pattern
D. All of the above
Answer : A
41. Process layout is also known as
A. Analytical-layout
B. Synthetic layout
C. Static product layout
D. None of these
Answer : A
42. The unit cost in case of batch production is ________ as compared to jobbing production.
A. Same
B. Low
C. High
D. None of these
Answer : B
43. A critical activity has
A. Maximum slack
B. Minimum slack
C. Zero slack
D. Average slack
Answer : C
44. Which one of the following represents a group incentive plan?
A. Scanlon Plan
B. Rowan Plan
C. Taylor Differential Piece Rate System
D. Halsey Premium Plan
Answer : A
45. In breakeven analysis, total cost consists of
A. Fixed cost
B. Variable cost
C. Fixed cost + variable cost
D. Fixed cost + variable cost + overheads
Answer : C
46. The critical path of a network represents
A. The minimum time required for completion of project
B. The maximum time required for completion of project
C. Maximum cost required for completion of project
D. Minimum cost required for completion of project
Answer : A
47. The most suitable incentive plan for the maintenance section of an industry will be
A. Piece rate system
B. Group incentive plan
C. Profit sharing plans
D. Simplification
Answer : B
48. Pick up the correct statement from the following
A. Programmer evaluation and review technique is event oriented
B. Programmer evaluation and review technique is not event oriented
C. Critical path method is event oriented
D. None of the above
Answer : D
49. The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
A. (to + tp + tn)/3
B. (to + 2tp + tn)/4
C. (to + 4tp + tn)/5
D. (to + tp + 4tn)/6
Answer : D
50. Emergency rush order can be pushed more effectively in
A. Job production
B. Automatic production
C. Continuous production
D. Intermittent production
Answer : D

Sharing is caring