1. In CPM analysis,
A. Emphasis is given to activities
B. Uncertainties are not allowed
C. Activities are represented by arrows
D. All the above
Answer : D
2. The reduction in project time normally results in
A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
Answer : B
3. The most suitable type of equipment for compaction of cohesive soils is
A. Smooth-wheeled rollers
B. Vibratory rollers
C. Sheep foot rollers
D. Tampers
Answer : C
4. For the execution of a project, a contractor is
A. A person
B. A firm
C. An agency
D. All the above
Answer : D
5. Frequency distribution curves
A. Having a single lump, are called uninodal curves
B. If symmetrical, are called normal curves
C. If not symmetrical, are called skew curves
D. All the above
Answer : D
6. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
7. The main principle of an organisation, is
A. Unity of command
B. Effective control at all levels
C. Delegation of authority
D. All the above
Answer : D
8. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A. 8 days
B. 9 days
C. 10 days
D. 15 days
Answer : B
9. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
Answer : A
10. Mobilization advance up to 10% of the cost of work is given to a contractor
A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and other staff
D. For all activities required to start the work at site on finalization of the contract document
Answer : D
11. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
A. 2.3% and 84.1%
B. 97.7% and 84.1%
C. 97.7 % and 15.9%
D. 15.9% and 97.7%
Answer : A
12. For excavating utility trenches with precise control of depth, the excavation equipment used is
A. Hoe
B. Shovel
C. Dragline
D. None of the above
Answer : A
13. Select the incorrect statement.
A. Start float and finish float are always equal.
B. Total float can be either start float or finish float.
C. Start float and finish float need not be equal.
D. Start float and finish float are the differences between activity times and not event times.
Answer : C
14. A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
C. Does not consume time
D. All the above
Answer : D
15. Frederick W. Taylor introduced a system of working known as
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. Effective organisation
Answer : C
16. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

A. 19
B. 14
C. 24
D. None of these
Answer : A
17. PERT is
A. An analytic in concept
B. Limited of event oriented diagrams
C. Used for research and development projects
D. All the above
Answer : D
18. For completion of a project, the critical path of the network represents
A. Minimum time
B. Maximum time
C. Maximum cost
D. Minimum cost
Answer : A
19. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A. Total float
B. Free float
C. Interfering float
D. Independent float
Answer : D
20. The performance of a specific task in CPM, is known
A. Dummy
B. Event
C. Activity
D. Contract
Answer : C
21. A critical ratio scheduling
A. Determines the status of each activity
B. Adjusts automatically changes in activity progress
C. Is a dynamic system
D. None of these
Answer : D
22. While scheduling a project by C.P.M.
A. A project is divided into various activities
B. Required time for each activity is established
C. Net work is drawn by connecting the activities and the events
D. All the above
Answer : D
23. During the construction period, price variation clause in contracts caters to
A. Increase in rates of only important materials
B. Variation in cost in materials element, labour element and petrol-oillubricant element
C. Variation in total cost of the project on an ad hoc basis
D. Rate of inflation
Answer : B
24. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
A. Concrete
B. Loose sand
C. Asphalt
D. Firm earth
Answer : B
25. In the given figure, the network of a project represents

A. Activity of an excavation of a footing
B. Activity of an excavation which starts at event No. 1 and ends at even No. 2
C. Activity of excavation which takes 8 units of time
D. None of these
Answer : C
26. An event is indicated on the network by a number enclosed in
A. A circle
B. A square
C. A triangle
D. All the above
Answer : D
27. For a given size of bucket, the ideal output of a dragline will be least in
A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay
Answer : D
28. A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
A. Rs. 1740
B. Rs. 3480
C. Rs. 5220
D. Rs. 6960
Answer : B
29. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
A. Duration
B. Total float
C. Free float
D. Interfering float
Answer : C
30. Henry Gantt developed Bar charts for planning and scheduling of projects in
A. 1880
B. 1900
C. 1920
D. 1940
Answer : B
31. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
A. Only (i) is correct
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
Answer : C
32. Critical path method
A. Is an improvement upon bar chart method
B. Provides a realistic approach to daily problems
C. Avoids delays which are very common in bar charts
D. All the above
Answer : D
33. Time and progress chart of a construction, is also known as
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. All the above
Answer : D
34. A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
Answer : D
35. In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
A. Yes, because of heavier overheads and handling cost
B. Yes, because of the very high order of quality control for the factory made components
C. No, because of repetitive manufacture of a number of elements
D. No, because of savings in site labour
Answer : C
36. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
Answer : D
37. Sensitivity analysis is a study of
A. Comparison of profit and loss
B. Comparison of assets and liabilities
C. Change in output due to change in input
D. Economics of cost and benefits of the project
Answer : C
38. Power stations are generally treated as
A. Light construction
B. Heavy construction
C. Industrial construction
D. Electrical construction
Answer : C
39. Whenever an activity has zero total float, then
A. Free float of the activity must be zero but independent float need not be zero
B. Independent float must be zero but free float need not be zero
C. Free float and independent float both must be zero
D. Free float and independent float both need not be zero
Answer : C
40. Pick up the correct statement from the following:
A. Forward pass is used for calculating earliest expected time
B. Backward pass is used for calculating the latest occurrence time
C. Maximum value of earliest expected time is used if there is more than one value of any event
D. All the above
Answer : D
41. The difference between the time avail-to do a job and the time required to do the job, is known as
A. Event
B. Float
C. Duration
D. Constraint
Answer : B
42. Crash project duration is obtained by summing the
A. Normal durations for all the activities
B. Crash durations for all activities
C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Answer : D
43. Economic saving of time results by crashing
A. Cheapest critical activity
B. Cheapest noncritical activity
C. Costliest critical activity
D. Costliest noncritical activity
Answer : A
44. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
A. (a + m + b)/6
B. (a + 2m + b)/6
C. (a + 4m + b)/6
D. (a + 5m + b)/6
Answer : C
45. Select the correct statement.
A. Activity arrows in a CPM network are drawn to scale
B. The tail of an arrow represents the finish of an activity
C. Arrow bead represents the start of an activity
D. None of the above
Answer : D
46. A Milestone chart
A. Shows the interdependencies of various jobs
B. Depicts the delay of jobs, if any
C. Points outgoing ahead of schedule of jobs, if any
D. None of these
Answer : D
47. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
A. LST-EST
B. LFT-EFT
C. TL-EFT
D. All the above
Answer : D
48. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
A. 80 and 90
B. 90 and 80
C. 85 and 75
D. 75 and 83
Answer : D
49. The final selection of a construction site, is done by
A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
D. All the above
Answer : D
50. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
A. Started 5 days later
B. Completed 5 days later
C. Performed at slower rate in 15 days
D. All the above
Answer : D