Question No : 22
In the method of tube boring of soil investigation, the following is essential:

A tube of about 2 metres length and 20 cm diameter with a cutting edge
A flap valve at the bottom of tube is provided to extract the soil sample
The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand
All the above

Question No : 23
In clay soil

Swelling and shrinkage characteristics prevail
Consolidation continues even after several years of construction
Differential settlement is generally prevalent
All the above

Question No : 24
The triangular portion between any two adjacent arches and the tangent to their crowns, is

Haunch
Spandril
Soffit
Rise

Question No : 25
The maximum bearing capacity of soil is that of

Black cotton soil
Loose fine sandy soil
Dry coarse sandy soil
Hard rocks

Question No : 26
The maximum total settlement for isolated foundations on clayey soils should be limited to

25 mm
40 mm
65 mm
100 mm

Question No : 27
Pick up the correct statement from the following:

In a king post truss, principal rafter and tie beams are jointed together with a bridle joint
Joint between the principal rafter and the king post is made by making tenon and mortise respectively
Joint between strut and king post, is generally of mortise and tenon type
All the above

Question No : 28
The inclined support at the ends of treads and rises of a stair, is known as

Baluster
Header
String
Beam