Question No : 15
The technique for establishing and maintaining priorities among the various jobs of a project, is known

Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling

Question No : 16
Pick up the incorrect statement from the following:

The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network

Question No : 17
In the given figure, the network of a project represents

Activity of an excavation of a footing
Activity of an excavation which starts at event No. 1 and ends at even No. 2
Activity of excavation which takes 8 units of time
None of these

Question No : 18
Critical path lies along the activities having total float

Positive
Negative
Zero
Same

Question No : 19
Which of the following is a weakness of bar chart?

Interdependencies of activities
Project progress
Uncertainties
All of the above

Question No : 20
Henry Gantt developed Bar charts for planning and scheduling of projects in

1880
1900
1920
1940

Question No : 21
The object of technical planning, is

Preparation of specifications
Preparation of estimates
Initiating the procurement action of resources
All the above