Home
Current Affairs January 2024

What is the correct answer?

4

A-B-C analysis

A. Is a basic technique of materials management

B. Is meant for relative inventory control

C. Does not depend upon the unit cost of the item but on its annual consumption

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

Monte Carlo solutions in queuing theory are extremely useful in queuing problems

A. That can't be analysed mathematically

B. Involving multistage queuing

C. To verify mathematical results

D. All of the above

What is the correct answer?

4

The probability distribution of activity times in PERT follows following distribution

A. Normal

B. Binomial

C. Beta

D. Exponential

What is the correct answer?

4

Product layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Military organisation is known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. All of the above

What is the correct answer?

4

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

A. Consumes time, but no resources

B. Consumes resources but no time

C. Consumes neither time nor resources

D. Is a dangling event

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system

B. Primary cost method

C. Current value method

D. Fixed price method

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?

A. Halsey plan

B. Gantt plan

C. Rowan plan

D. Emerson's efficiency plan

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

In CPM, the cost slope is determined by

A. Crash cost/Normal Cost

B. (Crash Cost - Normal cost)/ (Normal time - Crash time)

C. Normal Cost/Crash cost

D. (Normal cost - Crash cost)/ (Normal time - Crash time)

What is the correct answer?

4

According to Muther, the basic principle of best layout is

A. Principle of overall integration

B. Principle of flow

C. Principle of flexibility

D. All of these

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Scanlon Plan

B. Rowan Plan

C. Taylor Differential Piece Rate System

D. Halsey Premium Plan

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

Which one of the following techniques is used for determining allowances in time study?

A. Acceptance sampling

B. Linear regression

C. Performance rating

D. Work sampling

What is the correct answer?

4

Works cost implies

A. Primary cost

B. Factory cost

C. Factory expenses

D. Primary cost + factory expenses

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

The factors to be considered for production scheduling are

A. Component design

B. Route sheet

C. Time standards

D. All of these

What is the correct answer?

4

The unit cost in case of batch production is ________ as compared to jobbing production.

A. Same

B. Low

C. High

D. None of these

What is the correct answer?

4

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A. Early finish

B. Early start

C. Late start

D. Late finish

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

Product layout is best suited where

A. One type of product is produced

B. Product is standardised

C. Product is manufactured in large quantities

D. All of the above

What is the correct answer?

4

In manufacturing management, the term 'Dispatching' is used to describe

A. Dispatch of sales order

B. Dispatch of factory mail

C. Dispatch of finished product of the user

D. Dispatch of work orders through shop floor