Home
Current Affairs January 2024

What is the correct answer?

4

A big advantage of PERT over Gantt charts is that in the former case

A. Activities and events are clearly shown

B. Early start and late finish of an activity are clearly marked

C. Activity times are clear

D. Interrelationship among activities is clearly shown.

Correct Answer :

D. Interrelationship among activities is clearly shown.


Related Questions

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

PERT is

A. An analytic tool in concept

B. Limit up of event oriented diagrams

C. Used for research and development projects

D. All of the above

What is the correct answer?

4

The purpose of micro-motion study is to

A. Assist in finding out the most efficient way of doing work

B. Train the individual operator regarding the motion economy principles

C. Help in collecting the motion time data for synthetic time standards

D. All of the above

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

ABC analysis deals with

A. Analysis of process chart

B. Flow of material

C. Ordering schedule of job

D. Controlling inventory costs money

What is the correct answer?

4

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view

B. Motion study observed on enhanced time intervals

C. Motion study of a sequence of operations conducted systematically

D. Study of man and machine conducted simultaneously

What is the correct answer?

4

At the breakeven point,

A. Total cost is more than the sales revenue

B. Total cost is less than the sales revenue

C. Total cost is equal to sales revenue

D. Fixed cost is equal to variable cost

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

The time taken by a trained worker to perform an operation, while working a steady pace, is known as

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

Queueing theory is used for

A. Inventory problems

B. Traffic congestion studies

C. Job-shop scheduling

D. All of the above

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

Which of the following organisation is preferred in automobile industry?

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line and staff organisations

What is the correct answer?

4

Which of the following organisations is best suited for steel plants

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line, staff and functional organisations

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the

A. Fixed cost line

B. Variable cost line

C. Total cost line

D. Sales revenue line

What is the correct answer?

4

The objective of time study is to determine the time required to complete a job by

A. Fast worker

B. Average worker

C. Slow worker

D. New entrant

What is the correct answer?

4

Motion study involves analysis of

A. Actions of operator

B. Layout of work place

C. Tooling and equipment

D. All of the above

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

The employees provident fund act is applicable to

A. All industries

B. All industries other than small and medium industries

C. Volunteers

D. The industries notified by Government

What is the correct answer?

4

Current assets include

A. Manufacturing plant

B. Manufacturing plant and equipment

C. Inventories

D. Common stock held by the firm