10 %
15 %
20 %
25 %
C. 20 %
Between ceiling and ground level
Between ceiling and floor level
Upto roof above ground level
Upto ceiling from the ground level
Highest point on the extrados of the arch
Highest point on the intrados of the arch
Skew-back of the arch
None of these
Are vertical wooden members
Is the upper horizontal wooden member
Is the lower horizontal wooden member
Are the intermediate horizontal wooden members
Cracks appear on the plastered surface in the form of hair cracks
In brick work, the efflorescence is removed by applying a solution of zinc sulphate and water
Excessive thermal variations in the backing or plaster causes the plaster to fall
All the above
Arches require more headroom to span the openings like doors, windows etc.
Arches require strong abutments to withstand arch thrust
Arches are difficult in construction
All of the above
Are cohesionless aggregates
Vary in size between 2 to 20 mm
Never swell when they come into contact with water
All the above
The function of foundation is to distribute the load of super structure over a large bearing area
No timbering is required for shallow trenches
Shallow foundations can be constructed on made-up soil
Black cotton soil is very good for foundation bed
Column footing
Grillage footing
Raft footing
All the above
Ridge
Hip
Valley
None of these
Cleat
Stop
Horn
None of these
Jambs
Posts
Reveals
Styles
Upper flange of top tier
Lower beam of lower tier
Ends of external beams
None to these
1 cm per metre length
2 cm per metre length
4 cm per metre length
5 cm per metre length
1 day
4 days
7 days
14 days
Queen closer
Bevelled closer
King closer
Half king closer
Round steps
Angular steps
Winders
Radial steps
Simplex pile
Franki pile
Pressure pile
Vibro pile
0°
30°
60°
90°
50 m
60 m
75 m
90 m
Platform
Relief
Rest
Landing
Cork flooring
Glass flooring
Wooden flooring
Linoleum flooring
The operation theatre unit to be detached as it requires sterilized zone but near the ward for the patients and doctor
The mortuary should be detached from the main circulation with a post-mortem room
Casualty unit should be provided a separate entrance
All the above
Cleat
Stop
Horn
None of these
Rafters
Purlins
Battens
Struts
10 m
15 m
20 m
40 m
One course of headers to three or five course of stretchers
Queen closer in provided in each heading course
The middle course of stretchers is started with a header to give proper vertical joints
All the above
0.5 m
0.7 m
0.9 m
1.2 m
Half brick
Queen closer
King closer
Bevelled closer
First class bricks are used
Vertical joints in alternate courses are kept in plumb line
Bats are used where necessary
All the above
Haunch
Spandril
Voussoirs
Skewbacks