Is represented by a dotted line
Is an artificial activity
Does not consume time or resources
All of these
D. All of these
Estimation of the percentage utilisation of machine tools
Estimating the percentage of the time consumed by various job activities
Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
All of the above
Analyse material handling
Determine inventory control difficulties
Plan material handling procedure and routes
All of the above
Batch production
Job production
Mass production
All of the above
Value analysis
Network analysis
Linear programming
Queuing theory
When work should start and how much work should be completed during a certain period
When work should complete
That how idle time can be minimized
Proper utilisation of machines
Critical path method is an improvement upon bar chart method
Critical path method provides a realistic approach to the daily problems
Critical path method avoids delays which are very common in bar chart
All of the above
Event
Float
Duration
Constraint
Operator's activity
Flow of material and in case of trouble locate source of trouble
Minimising the delays
Making efficient despatching
Adequate incentive
Ease of administration
Guaranteed basic pay
All of these
Total work content
Base time + relaxation time
Total work content + basic time
Total work content + delay contingency allowance
Is not applied to all level of workers
Is applied to all level of workers
Does not guarantee minimum wage
Is based upon efficiency of worker
Optimum lot size
Highest level of inventory
Lot corresponding to breakeven point
Capability of a plant to produce
Jobbing work economics are involved
Production is on large scale
Only few components are involved
Costly equipment is used
Total production cost is less
Material movement is less
Capital investment is minimum
All of these
Assembly industry
Process industry
Job order industry
Mass production industry
Is artificially introduced
Is represented by a dotted line
Does not require any time
All of the above
CAM < DAM
CAM > DAM
CAM = DAM
There is no such criterion
Line organisation
Functional organisation
Line and staff organisation
Line, staff and functional organisation
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with the starting of processes
Regulates the progress of job through various processes
Rowan Plan
Taylor Differential Piece rate system
Halsey Premium plan
Day work plan
All industries have to necessarily train the apprentices
Industries have to train apprentices according to their requirement
All industries employing more than 100 workers have to recruit apprentices
Only industries employing more than 500 workers have to recruit apprentices
Earliest start time + duration of activity
Earliest start time duration of activity
Latest finish time + duration of activity
Latest finish time duration of activity
Batch production
Continuous type of product
Effective utilisation of machines
All of the above
Manpower utilisation
Quality assurance of the product
Machine utilisation
Optimising material flow through the plant
Factory overheads
Factory and administration overheads
Factory, administration and sales overheads
Factory, administration, sales overheads and profit
Delphi
Brain storming
Morphological analysis
Direct expert comparison
Inventory control
Material handling
Production schedule
Machine repair schedules
Determining the most efficient method of performing a job
Establishing the minimum time of completion of a job
Developing the standard method and standard time of a job
Economising the motions involved on the part of the worker while performing a job
Overhead crane
Trolley
Belt conveyor
All of the above
Optimistic time
Pessimistic time
Most likely time
All of these