Home
Current Affairs January 2024

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

Correct Answer :

C. Satisfy the problem constraints and non-negativity restrictions


Related Questions

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

Pick up the correct statement from the following

A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed

B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project

D. All of the above

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

According to Muther, the basic principle of best layout is

A. Principle of overall integration

B. Principle of flow

C. Principle of flexibility

D. All of these

What is the correct answer?

4

According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)

A. CAM < DAM

B. CAM > DAM

C. CAM = DAM

D. There is no such criterion

What is the correct answer?

4

Micro-motion study is

A. Analysis of one stage of motion chart

B. Motion study, when seen on a time chart

C. Subdivision of an operation into therbligs and their analysis

D. Enlarged view of motion study

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

Which of the following statement is wrong?

A. An activity consumes time and resources whereas an event does not consume time or resources.

B. The performance of a specific task is called an activity.

C. An event is an instantaneous point in time at which an activity begins or ends.

D. The turning of a job on lathe is an event whereas job turned is an activity.

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction

What is the correct answer?

4

Critical path method

A. Helps in ascertaining time schedules

B. Makes better and detailed planning possible

C. Provides a standard method for communicating project plans schedules and to time and cost performance

D. All of the above

What is the correct answer?

4

Time study is

A. The appraisal, in terms of time, of the value of work involving human effort

B. Machine setting time

C. Time taken by workers to do a job

D. Method of fixing time for workers

What is the correct answer?

4

The appellate authority for an industrial dispute is

A. Management

B. Labour court

C. High court/supreme court

D. Board of directors

What is the correct answer?

4

A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the

A. Fixed cost line

B. Variable cost line

C. Total cost line

D. Sales revenue line

What is the correct answer?

4

Work sampling is applied for

A. Estimation of the percentage utilisation of machine tools

B. Estimating the percentage of the time consumed by various job activities

C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible

D. All of the above

What is the correct answer?

4

Breakeven point is the point where

A. Fixed and variable cost lines intersect

B. Fixed and total cost lines intersect

C. Variable and total cost lines intersect

D. Sales revenue and total expensive lines intersect

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

Work study involves

A. Only method study

B. Only work measurement

C. Method study and work measurement

D. Only motion study

What is the correct answer?

4

An event is indicated on the network by

A. A straight line

B. A number enclosed in a circle or a square

C. A straight line with circles at the ends

D. A dotted line

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

Indirect expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. All of these

What is the correct answer?

4

Break-even analysis shows profit when

A. Sales revenue > total cost

B. Sales revenue = total cost

C. Sales revenue < total cost

D. Variable cost < fixed cost

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

What is the correct answer?

4

Simplex method is the method used for

A. Value analysis

B. Network analysis

C. Linear programming

D. Queuing theory

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

Which of the following organisation is preferred in automobile industry?

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line and staff organisations

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

Positive slack on a PERT indicates that project is

A. Ahead of schedule

B. Beyond schedule

C. As per schedule

D. On critical path

What is the correct answer?

4

Inventory management consists of

A. Effective running of stores

B. State of merchandise methods of storing and maintenance etc.

C. Stock control system

D. All of the above

What is the correct answer?

4

A dummy activity in a net work diagram

A. Is represented by a dotted line

B. Is an artificial activity

C. Does not consume time or resources

D. All of these

What is the correct answer?

4

String diagram is used when

A. Team of workers is working at a place

B. Material handling is to be done

C. Idle time is to be reduced

D. All of the above