Home
Current Affairs January 2024

What is the correct answer?

4

A graphical device used to determine the breakeven point and profit potential under varying conditions of output and costs, is known as

A. Gantt chart

B. Flow chart

C. Breakeven chart

D. PERT chart

Correct Answer :

C. Breakeven chart


Related Questions

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of any project is known as

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

What is the correct answer?

4

Pick up the incorrect statement from the following

A. An activity of the project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn (to scale from) left to right

What is the correct answer?

4

Breakeven analysis is a

A. Short term analysis

B. Long term analysis

C. Average of short and long term analysis

D. Any one of these

What is the correct answer?

4

An event is indicated on the network by

A. A straight line

B. A number enclosed in a circle or a square

C. A straight line with circles at the ends

D. A dotted line

What is the correct answer?

4

Positive slack on a PERT indicates that project is

A. Ahead of schedule

B. Beyond schedule

C. As per schedule

D. On critical path

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

PERT/CPM, techniques can be used for following applications

A. Once through project

B. Maintenance jobs

C. Research and development

D. All of the above

What is the correct answer?

4

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth

B. One-half

C. Equal to

D. Twice

What is the correct answer?

4

In a PERT chart

A. All activities should be numbered

B. Only important activities should be numbered

C. Only critical activities are numbered

D. Only selected activities are numbered

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

Job enrichment technique is applied to

A. Reduce labour monotony

B. Overcome boring and de-motivating work

C. Make people happy

D. All of the above

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

Work sampling observations are taken on the basis of

A. Detailed calculations

B. Convenience

C. Table of random numbers

D. Past experience

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

The interchangeability can be achieved by

A. Standardisation

B. Better process planning

C. Bonus plan

D. Better product planning

What is the correct answer?

4

String diagram is used

A. For checking the relative values of various layouts

B. When a group of workers are working at a place

C. Where processes require the operator to be moved from one place to another

D. All of the above

What is the correct answer?

4

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system

B. Primary cost method

C. Current value method

D. Fixed price method

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

What is the correct answer?

4

The reasons which are basically responsible for the formation of a queue should be that

A. The average service rate Hess than the average arrival rate

B. Output rate is linearly proportional to input

C. Output rate is constant and the input varies in a random manner

D. All of the above

What is the correct answer?

4

Break-even analysis shows profit when

A. Sales revenue > total cost

B. Sales revenue = total cost

C. Sales revenue < total cost

D. Variable cost < fixed cost

What is the correct answer?

4

Choose the wrong statement Time study is used to

A. Determine overhead expenses

B. Provide a basis for setting piece prices or incentive wages

C. Determine standard costs

D. Determine the capability of an operator to handle the number of machines

What is the correct answer?

4

Which of the following is independent of sales forecast?

A. Productivity

B. Inventory control

C. Production planning

D. Production control

What is the correct answer?

4

Dispatching

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with the starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

Halsey plan of wage incentive

A. Is not applied to all level of workers

B. Is applied to all level of workers

C. Does not guarantee minimum wage

D. Is based upon efficiency of worker