Home
Current Affairs January 2024

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

Correct Answer :

C. Mass production


Related Questions

What is the correct answer?

4

Gantt charts are used for

A. Forecasting sales

B. Production schedule

C. Scheduling and routing

D. Linear programming

What is the correct answer?

4

The production cost per unit can be reduced by

A. Producing more with increased inputs

B. Producing more with the same inputs

C. Eliminating idle time

D. Minimising resource waste

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above

What is the correct answer?

4

The disadvantage of product layout is

A. High initial investment for the specialized facilities

B. Skilled labour to operate machines

C. Production time is longer, requiring more goods in inventory

D. High cost of inspection

What is the correct answer?

4

Expediting function consists in keeping a watch on

A. Operator's activity

B. Flow of material and in case of trouble locate source of trouble

C. Minimising the delays

D. Making efficient despatching

What is the correct answer?

4

Work study is done with the help of

A. Process chart

B. Material handling

C. Stop watch

D. All of the above

What is the correct answer?

4

Which of the following layouts is suited for mass production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Which of the following statement is wrong?

A. An activity consumes time and resources whereas an event does not consume time or resources.

B. The performance of a specific task is called an activity.

C. An event is an instantaneous point in time at which an activity begins or ends.

D. The turning of a job on lathe is an event whereas job turned is an activity.

What is the correct answer?

4

Choose the wrong statement Time study is used to

A. Determine overhead expenses

B. Provide a basis for setting piece prices or incentive wages

C. Determine standard costs

D. Determine the capability of an operator to handle the number of machines

What is the correct answer?

4

Bar chart is suitable for

A. Large project

B. Major work

C. Minor work

D. All of these

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

In the cost structure of a product, the selling price is determined by the factors such as

A. Sales turn over

B. Lowest competitive price

C. Various elements of the cost

D. All of the above

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

In which of the following layouts, the lines need to the balanced

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

In ABC control policy, maximum attention is given to

A. Those items which consume money

B. Those items which are not readily available

C. Those × items which are in more demand

D. Those items which consume more money

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

For a product layout the material handling equipment must

A. Have full flexibility

B. Employ conveyor belts, trucks, tractors etc.

C. Be a general purpose type

D. Be designed as special purpose for a particular application

What is the correct answer?

4

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system

B. A merit rating system

C. A job evaluation system

D. His individual performance

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

Current assets include

A. Manufacturing plant

B. Manufacturing plant and equipment

C. Inventories

D. Common stock held by the firm

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

ABC analysis deals with

A. Analysis of process chart

B. Flow of material

C. Ordering schedule of job

D. Controlling inventory costs money

What is the correct answer?

4

In manufacturing management, the term 'Dispatching' is used to describe

A. Dispatch of sales order

B. Dispatch of factory mail

C. Dispatch of finished product of the user

D. Dispatch of work orders through shop floor

What is the correct answer?

4

Job enrichment technique is applied to

A. Reduce labour monotony

B. Overcome boring and de-motivating work

C. Make people happy

D. All of the above