Principle of overall integration
Principle of flow
Principle of flexibility
All of these
D. All of these
Forecasting sales
Production schedule
Scheduling and routing
Linear programming
A job
An individual employee
A particular division in workshop
Machine
When work should start and how much work should be completed during a certain period
When work should complete
That how idle time can be minimized
Proper utilisation of machines
Analysis of a man-work method by using a motion picture camera with a timing device in the field of view
Motion study observed on enhanced time intervals
Motion study of a sequence of operations conducted systematically
Study of man and machine conducted simultaneously
Batch production
Job production
Mass production
All of the above
Optimistic time
Pessimistic time
Most likely time
All of these
Annual cost method
Rate of return method
Total life average method
Any one of the above
Sales turn over
Lowest competitive price
Various elements of the cost
All of the above
When slack of an activity is zero, it falls only on critical path.
CPM technique is useful to minimise the direct and indirect expenses.
Critical path of a net work represents the minimum time required for completion of project.
All of the above
Job production
Batch production
Mass production
Any one of these
Credited into reserves of company
Deposited in nationalised bank
Deposited in post office
Deposited in the account of worker with Provident Fund Commissioner
Belt conveyor
Bucket conveyor
Fork lift truck
Overhead crane
Operation
Inspection
Delay/ temporary Storage
Permanent storage
Differential piece rate system
Rowan plan
Emerson plan
Taylor plan
Where production activities are involved
In judging the rating of machines
In improving industrial relations
In judging the output of a man and improving it
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling
Optimistic time
Pessimistic time
Most likely time
All of these
Product layout
Functional layout
Automatic material handling equipment
Specialisation of operation
Overhead crane
Trolley
Belt conveyor
All of the above
Have full flexibility
Employ conveyor belts, trucks, tractors etc.
Be a general purpose type
Be designed as special purpose for a particular application
Sugar industries
Oil refining industries
Spinning and weaving industries
All of these
Acceptance sampling
Linear regression
Performance rating
Work sampling
Helps in ascertaining time schedules
Makes better and detailed planning possible
Provides a standard method for communicating project plans schedules and to time and cost performance
All of the above
A straight line
A number enclosed in a circle or a square
A straight line with circles at the ends
A dotted line
Latest start time of succeeding event earliest finish time of preceding event activity time
Latest start time of the event earliest start time of the event
Latest finish time of event earliest finish time of the event
Anyone of the above
The appraisal, in terms of time, of the value of work involving human effort
Machine setting time
Time taken by workers to do a job
Method of fixing time for workers
Top level executives have to do excessive work
Structure is rigid
Communication delays occur
All of the above
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with the starting of processes
Regulates the progress of job through various processes
Normal distribution
Poissons distribution
Erlang distribution
Exponential law
It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
The activity is critical and any delay in its performance will delay the completion of whole project
Any one of the above