Home
Current Affairs January 2024

What is the correct answer?

4

After casting, an ordinary cement concrete on drying

A. Expands

B. Mix

C. Shrinks

D. None of these

Correct Answer :

C. Shrinks


Related Questions

What is the correct answer?

4

An aggregate is said to be flaky, if its least dimension is less than

A. 2/3 mean dimension

B. 3/4 mean dimension

C. 3/5 mean dimension

D. 5/8 mean dimension

What is the correct answer?

4

Select the incorrect statement

A. The loss of pre-stress is more in pre-tensioning system than in posttensioning system.

B. Pre-tensioning system has greater certainty about its durability.

C. For heavy loads and large spans in buildings or bridges, posttensioning system is cheaper than pre-tensioning system

D. None of the above

What is the correct answer?

4

The following proportion of the ingredients of concrete mix, is not in conformation to arbitrary method of proportioning

A. 1 : 1 : 2

B. 1 : 2 : 4

C. 1 : 3 : 6

D. 1 : 4 : 10

What is the correct answer?

4

Le-Chatelier's apparatus is used for testing

A. Soundness of cement

B. Hardness of cement

C. Strength of cement

D. Durability of cement

What is the correct answer?

4

The ratio of various ingredients (cement, sand, aggregates) in concrete of grade M 200, is

A. 1 : 2 : 4

B. 1 : 3 : 6

C. 1 : 1 ½ : 3

D. 1 : 1 : 2

What is the correct answer?

4

To ensure constant moisture content in aggregates

A. Area of each aggregate pile should be large

B. Height of each aggregate pile should not exceed 1.50 m

C. Aggregate pile should be left for 24 hours before aggregates are used

D. All the above

What is the correct answer?

4

If fineness modulus of sand is 2.5, it is graded as

A. Very fine sand

B. Fine sand

C. Medium sand

D. Coarse sand

What is the correct answer?

4

A concrete having a slump of 6.5 cm, is said to be

A. Dry

B. Earth moist

C. Semi-plastic

D. Plastic

What is the correct answer?

4

Pozzolana cement is used with confidence for construction of

A. Dams

B. Massive foundations

C. R.C.C. structures

D. All the above

What is the correct answer?

4

The commercial name of white and coloured cement in India, is

A. Colorcrete

B. Silvicrete

C. Snowcem

D. All the above

What is the correct answer?

4

As compared to ordinary Portland cement, high alumina cement has

A. Higher initial setting time but lower final setting time

B. Lower initial setting time but higher final setting time

C. Higher initial and final setting times

D. Lower initial and final setting times

What is the correct answer?

4

Segregation is responsible for

A. Honey-combed concrete

B. Porous layers in concrete

C. Surface scaling in concrete

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The weight of ingredients of concrete mix, is taken in kilograms

B. Water and aggregates are measured in litres

C. 20 bags of cement make one tonne

D. All the above

What is the correct answer?

4

Gypsum is added for

A. Colour

B. Strength

C. Controlling setting time

D. None of these

What is the correct answer?

4

The operation of removing humps and hollows of uniform concrete surface, is known as

A. Floating

B. Screeding

C. Trowelling

D. Finishing

What is the correct answer?

4

The factor of safety for

A. Steel and concrete are same

B. Steel is lower than that for concrete

C. Steel is higher than that for concrete

D. None of the above

What is the correct answer?

4

Admixtures which cause early setting and hardening of concrete are called

A. Workability admixtures

B. Accelerators

C. Retarders

D. Air entraining agents

What is the correct answer?

4

Pick up the correct statement from the following:

A. Continuous grading is not necessary for obtaining a minimum of air voids

B. The omission of a certain size of aggregate is shown by a straight horizontal line on the grading curve

C. The omission of a certain size of aggregate in concrete increases the workability but also increases the liability to segregation

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The free water is the amount of water added while mixing and the amount of water held on the surface of the aggregates prior to mixing

B. The total water is the free water and the amount actually absorbed by the aggregates

C. Neither (a) nor (b)

D. Both (a) and (b)

What is the correct answer?

4

Too wet concrete may cause

A. Weakness of concrete

B. Excessive laitance

C. Segregation

D. All the above

What is the correct answer?

4

For the construction of the retaining structures, the type of concrete mix to be used, is

A. 1 : 3 : 6

B. 1 : 2 : 4

C. 1 : 1 ½ : 3

D. 1 : 4 : 8

What is the correct answer?

4

Allowable shear strength of concrete, depends upon

A. Shear strength

B. Tensile strength

C. Compressive strength

D. None of these

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. With passage of time, the strength of cement increases

B. With passage of time, the strength of cement decreases

C. After a period of 24 months, the strength of cement reduces to 50%

D. The concrete made with storage deteriorated cement, gains strength with time

What is the correct answer?

4

An ordinary Portland cement when tested for its fineness, should not leave any residue on I.S. sieve No. 9, more than

A. 5 %

B. 10 %

C. 15 %

D. 20 %

What is the correct answer?

4

Air entrainment in the concrete increases

A. Workability

B. Strength

C. The effects of temperature variations

D. The unit weight

What is the correct answer?

4

Assertion A : The load factor for live load is greater than that for dead load. Reason R : The live loads are more uncertain than dead loads. Select your answer based on the coding system given below:

A. Both A and R is true and R is the correct explanation of A

B. Both A and R is true but R is not the correct explanation of A

C. A is true but R is false

D. A is false but R is true

What is the correct answer?

4

For a longitudinal reinforcing bar in a column, the minimum cover shall neither be less than the diameter of bar nor less than

A. 15 mm

B. 25 mm

C. 30 mm

D. 40 mm

What is the correct answer?

4

The 28 days cube strength of mass concrete using aggregates of maximum size 5 cm for gravity dams should be

A. Between 150 to 300 kg/cm2

B. Between 350 to 600 kg/cm2

C. Between 150 to 500 kg/cm2

D. Below 200 kg/cm2

What is the correct answer?

4

Which of the following losses of pre-stress occurs only in pretensioning and not in post-tensioning?

A. Elastic shortening of concrete

B. Shrinkage of concrete

C. Creep of concrete

D. Loss due to friction

What is the correct answer?

4

The permissible diagonal tensile stress in reinforced brick work is

A. About 0.1 N/mm²

B. Zero

C. 0.3 N/mm² to 0.7 N/mm²

D. About 1.0 N/mm²