Home
Current Affairs January 2024

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

Correct Answer :

C. An arrow


Related Questions

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

PERT/CPM, techniques can be used for following applications

A. Once through project

B. Maintenance jobs

C. Research and development

D. All of the above

What is the correct answer?

4

The production cost per unit can be reduced by

A. Producing more with increased inputs

B. Producing more with the same inputs

C. Eliminating idle time

D. Minimising resource waste

What is the correct answer?

4

The allowed time for a job equals standard time plus

A. Policy allowance

B. Interference allowance

C. Process allowance

D. Learning allowance

What is the correct answer?

4

In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches

A. 50 %

B. 66.67 %

C. 75 %

D. 80 %

What is the correct answer?

4

The factors which are to be considered while developing a good wage incentive plan will include

A. Adequate incentive

B. Ease of administration

C. Guaranteed basic pay

D. All of these

What is the correct answer?

4

If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be

A. 2 HA

B. 1.33 HA

C. 1.5 HA

D. 1.15 HA

What is the correct answer?

4

Which of the following type of layout is suitable for automobile manufacturing concern?

A. Product layout

B. Process layout

C. Fixed position layout

D. Combination layout

What is the correct answer?

4

Work study is most useful

A. Where production activities are involved

B. In judging the rating of machines

C. In improving industrial relations

D. In judging the output of a man and improving it

What is the correct answer?

4

PERT has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

The deductions for, employees provident fund start

A. Immediately on joining the service

B. After 60 days of joining the service

C. After 100 days of joining the service

D. After 240 days of joining the service

What is the correct answer?

4

In order that linear programming techniques provide valid results

A. Relations between factors must be linear (positive)

B. Relations between factors must be linear (negative)

C. Either (A) or (B)

D. Only one factor should change at a time, others remaining constant

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack

What is the correct answer?

4

The most important function of inventory control is

A. Stock control system

B. To run the stores effectively

C. Technical responsibility for the state of materials

D. All of the above

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Monte Carlo solutions in queuing theory are extremely useful in queuing problems

A. That can't be analysed mathematically

B. Involving multistage queuing

C. To verify mathematical results

D. All of the above

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

What is the correct answer?

4

If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by

A. AP/C

B. 2AP/C

C. √(AP/C)

D. (AP/C)2

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

Father of time study was

A. F.W. Taylor

B. H.L. Gantt

C. F.B. Gilbert

D. R.M. Barnes

What is the correct answer?

4

In the cost structure of a product, the selling price is determined by the factors such as

A. Sales turn over

B. Lowest competitive price

C. Various elements of the cost

D. All of the above

What is the correct answer?

4

Dispatching

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with the starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as

A. Event

B. Free float

C. Artificial

D. Dummy

What is the correct answer?

4

Product layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Which of the following conditions are necessary for applying linear programming?

A. These must be a well defined objective function.

B. The decision variables should be interrelated and nonnegative.

C. The resources must be in limited supply.

D. All of the above

What is the correct answer?

4

The correct sequence of phases in value engineering is

A. Creative phase, information phase, investigation phase, evaluation phase

B. Information phase, creative phase, investigation phase, evaluation phase

C. Investigation phase, information phase, creative phase, evaluation phase

D. Creative phase, investigation phase, evaluation phase, information phase