Home
Current Affairs January 2024

What is the correct answer?

4

CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

Correct Answer :

A. One time estimate


Related Questions

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

Material handling and plant location is analysed by

A. Gantt chart

B. Bin chart

C. Emerson chart

D. Travel chart

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

What is the correct answer?

4

The important file in making a PERT is

A. An event can't be accomplished until activities leading to it are completed

B. No activity from any event can be started from preceding event till it is completed

C. Length of arrow has nothing to do with time

D. All of the above

What is the correct answer?

4

Micro-motion study involves following number of fundamental hand motions

A. 8

B. 12

C. 16

D. 20

What is the correct answer?

4

Pessimistic time is

A. The maximum time which an activity might require

B. The average time required for a job

C. The most probable time considering all conditions

D. The minimum time in which an activity can possibly be accomplished

What is the correct answer?

4

Job enrichment technique is applied to

A. Reduce labour monotony

B. Overcome boring and de-motivating work

C. Make people happy

D. All of the above

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

Process layout is also known as

A. Analytical-layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth

B. One-half

C. Equal to

D. Twice

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

Production cost refers to prime cost plus

A. Factory overheads

B. Factory and administration overheads

C. Factory, administration and sales overheads

D. Factory, administration, sales overheads and profit

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

Routing is essential in the following type of industry

A. Assembly industry

B. Process industry

C. Job order industry

D. Mass production industry

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

PERT is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system

B. Primary cost method

C. Current value method

D. Fixed price method

What is the correct answer?

4

The production cost per unit can be reduced by

A. Producing more with increased inputs

B. Producing more with the same inputs

C. Eliminating idle time

D. Minimising resource waste

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programmes

C. Is used for repetitive works

D. All of the above

What is the correct answer?

4

Monte Carlo solutions in queuing theory are extremely useful in queuing problems

A. That can't be analysed mathematically

B. Involving multistage queuing

C. To verify mathematical results

D. All of the above

What is the correct answer?

4

In breakeven analysis, total cost consists of

A. Fixed cost

B. Variable cost

C. Fixed cost + variable cost

D. Fixed cost + variable cost + overheads

What is the correct answer?

4

In inventory control, the economic order quantity is the

A. Optimum lot size

B. Highest level of inventory

C. Lot corresponding to breakeven point

D. Capability of a plant to produce

What is the correct answer?

4

In Halsey 50-50 plan, output standards are established

A. By time study

B. From previous production records

C. From one's judgement

D. All of the above

What is the correct answer?

4

Gantt chart provides information about the

A. Material handling

B. Proper utilisation of manpower

C. Production schedule

D. Efficient working of machine