Home
Current Affairs January 2024

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

Correct Answer :

A. Single time estimate


Related Questions

What is the correct answer?

4

The factors which are to be considered while developing a good wage incentive plan will include

A. Adequate incentive

B. Ease of administration

C. Guaranteed basic pay

D. All of these

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction

What is the correct answer?

4

The bonus increases in proportion to the increase in efficiency. This statement applies to

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

What is the correct answer?

4

In a functional organisation

A. Quality of work is better

B. Wastage of material is minimum

C. Specialised knowledge and guidance to individual worker is provided

D. All of the above

What is the correct answer?

4

Which of the following is independent of sales forecast?

A. Productivity

B. Inventory control

C. Production planning

D. Production control

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

Slack represents the difference between the

A. Latest allowable time and the normal expected time

B. Latest allowable time and the earliest expected time

C. Proposed allowable time and the earliest expected time

D. Normal allowable time and the latest expected time

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

The probability distribution of activity times in PERT follows following distribution

A. Normal

B. Binomial

C. Beta

D. Exponential

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of any project is known as

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

A dummy activity in a net work diagram

A. Is represented by a dotted line

B. Is an artificial activity

C. Does not consume time or resources

D. All of these

What is the correct answer?

4

Military organisation is known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. All of the above

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

The employees provident fund act is applicable to

A. All industries

B. All industries other than small and medium industries

C. Volunteers

D. The industries notified by Government

What is the correct answer?

4

The type of organisation preferred for an automobile industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

In Halsey 50-50 plan, output standards are established

A. By time study

B. From previous production records

C. From one's judgement

D. All of the above

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

One of the basic essentials of an incentive plan is that

A. A differential piece rate system should exist

B. Minimum wages should be guaranteed

C. Provide incentive to group efficiency performance

D. All standards should be based on time studies

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

Work sampling is applied for

A. Estimation of the percentage utilisation of machine tools

B. Estimating the percentage of the time consumed by various job activities

C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible

D. All of the above