Operator's activity
Flow of material and in case of trouble locate source of trouble
Minimising the delays
Making efficient despatching
B. Flow of material and in case of trouble locate source of trouble
To produce better quality of product
To utilise maximum floor area
To minimise production delays
All of these
The average service rate Hess than the average arrival rate
Output rate is linearly proportional to input
Output rate is constant and the input varies in a random manner
All of the above
TR
TR + [(S - T)/2] × R
TR + (S - T) × R
TR + [(S - T)/S] × R
Gantt chart
Flow chart
Breakeven chart
PERT chart
Strict adherence to specification
Separation of planning and design part
Each individual maintains functional efficiency
All of the above
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
Actions of operator
Layout of work place
Tooling and equipment
All of the above
Ordering procedure
Forecasting sales
Production planning
Despatching and expediting
Effective running of stores
State of merchandise methods of storing and maintenance etc.
Stock control system
All of the above
Maximum slack
Minimum slack
Zero slack
Average slack
A planning layout
Flow of material
Advancing a programme in automatic machines
Copying complicated profiles
8
12
16
20
Process layout
Product layout
Fixed position layout
Plant layout
Latest start time earliest start time
Latest finish time earliest finish time (EFT)
TLEFT
All of the above
Event
Float
Duration
Constraint
Event
Free float
Artificial
Dummy
Product layout
Process layout
Fixed position layout
Combination layout
Improve existing methods
Establish time standards
Develop effective methods in advance of the beginning of production
All of the above
String diagram
Flow process chart
Travel chart
Flow diagram
F.W. Taylor
H.L. Gantt
F.B. Gilbert
R.M. Barnes
Operation research
Linear programming
Network analysis
Breakeven analysis
Operation
Inspection
Delay/ temporary Storage
Permanent storage
Free float = total float
Independent float = total float
Independent float > free float
Independent float < free float
(to + tp + tn)/3
(to + 2tp + tn)/4
(to + 4tp + tn)/5
(to + tp + 4tn)/6
Improving present method and finding standard time
Motivation of workers
Improving production capability
Improving production planning and control
All industries
All industries other than small and medium industries
Volunteers
The industries notified by Government
Observed performance + normal performance
Observed performance - normal performance
Observed performance × normal performance
None of the above
Halsey Premium Plan
Lincoln Plan
Rowan Plan
Taylor Plan
The most economical level of operation of any industry
The time when unit can run without i loss and profit
Time when industry will undergo loss
The time when company can make maximum profits
Fast worker
Average worker
Slow worker
New entrant