Home
Current Affairs January 2024

What is the correct answer?

4

Father of industrial engineering is

A. Jack Gilbert

B. Gantt

C. Taylor

D. Newton

Correct Answer :

B. Gantt


Related Questions

What is the correct answer?

4

Which of the following is independent of sales forecast?

A. Productivity

B. Inventory control

C. Production planning

D. Production control

What is the correct answer?

4

A dummy activity in a net work diagram

A. Is represented by a dotted line

B. Is an artificial activity

C. Does not consume time or resources

D. All of these

What is the correct answer?

4

Pick up the correct statement from the following

A. Critical path method is an improvement upon bar chart method

B. Critical path method provides a realistic approach to the daily problems

C. Critical path method avoids delays which are very common in bar chart

D. All of the above

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

The main objective of work measurement is to

A. Plan and schedule of production

B. Formulate a proper incentive scheme

C. Estimate the selling prices and delivery dates

D. All of the above

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

In fixed position layout

A. Total production cost is less

B. Material movement is less

C. Capital investment is minimum

D. All of these

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if

A. Complete details of items in, waiting line are known

B. Arrival and waiting times are known and can be grouped to form a waiting line model

C. All variables and constants are known and form a linear equation

D. The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known

What is the correct answer?

4

Pessimistic time is

A. The maximum time which an activity might require

B. The average time required for a job

C. The most probable time considering all conditions

D. The minimum time in which an activity can possibly be accomplished

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

Job enrichment technique is applied to

A. Reduce labour monotony

B. Overcome boring and de-motivating work

C. Make people happy

D. All of the above

What is the correct answer?

4

The first method invented for planning projects was

A. Bar chart method

B. Milestone chart

C. Critical path method (CPM)

D. Programme evaluation and review technique (PERT)

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

What is the correct answer?

4

In micro-motion study, therblig is described by

A. A symbol

B. An event

C. An activity

D. Standard symbol and colour

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner

What is the correct answer?

4

In time study, the rating factor is applied to determine

A. Standard time of a job

B. Merit rating of the worker

C. Fixation of incentive rate

D. Normal time of a worker

What is the correct answer?

4

In a PERT chart

A. All activities should be numbered

B. Only important activities should be numbered

C. Only critical activities are numbered

D. Only selected activities are numbered

What is the correct answer?

4

In a functional organisation

A. Quality of work is better

B. Wastage of material is minimum

C. Specialised knowledge and guidance to individual worker is provided

D. All of the above

What is the correct answer?

4

Process layout is employed for

A. Batch production

B. Continuous type of product

C. Effective utilisation of machines

D. All of the above

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)

A. (to + tp + tn)/3

B. (to + 2tp + tn)/4

C. (to + 4tp + tn)/5

D. (to + tp + 4tn)/6

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor