Home
Current Affairs January 2024

What is the correct answer?

4

For a slab supported on its four edges with corners held down and loaded uniformly, the Marcus correction factor to the moments obtained by Grashoff Rankine's theory

A. Is always less than 1

B. Is always greater than 1

C. Can be more than 1

D. Can be less than 1

Correct Answer :

A. Is always less than 1


Related Questions

What is the correct answer?

4

Poisson's ratio for concrete

A. Remains constant

B. Increases with richer mixes

C. Decreases with richer mixes

D. None of the above

What is the correct answer?

4

You are asked to construct a massive dam, the type of cement you will use, is

A. Ordinary Portland cement

B. Rapid hardening cement

C. Low heat cement

D. Blast furnace slag cement

What is the correct answer?

4

According to Water-Cement Ratio Law, the strength of workable plastic concrete

A. Depends upon the amount of water used in the mix

B. Does not depend upon the quality of cement mixed with aggregates

C. Does not depend upon the quantity of cement mixed with aggregates

D. All the above

What is the correct answer?

4

In order to obtain the best workability of concrete, the preferred shape of aggregate is

A. Rounded

B. Elongated

C. Angular

D. All of the above

What is the correct answer?

4

According to Whitney's theory, depth of stress block for a balanced section of a concrete beam is limited to

A. 0.43 d

B. 0.537 d

C. 0.68 d

D. 0.85 d Where d is effective depth of beam

What is the correct answer?

4

According to IS: 4561978, the maximum reinforcement in a column is

A. 2 %

B. 4 %

C. 6 %

D. 8 %

What is the correct answer?

4

Higher workability of concrete is required if the structure is

A. Made with cement concrete

B. Thick and reinforced

C. Thin and heavily reinforced

D. Thick and heavily reinforced

What is the correct answer?

4

For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:

A. 70 litres of sand and 120 litres of aggregates

B. 70 kg of sand and 140 litres of aggregates

C. 105 litres of sand and 140 litres of aggregates

D. 105 litres of sand and 210 litres of aggregates

What is the correct answer?

4

For a simply supported beam of span 15 m, the minimum effective depth to satisfy the vertical deflection limits should be

A. 600 mm

B. 750 mm

C. 900 mm

D. More than 1 m

What is the correct answer?

4

For a reinforced concrete section, the shape of shear stress diagram is

A. Wholly parabolic

B. Wholly rectangular

C. Parabolic above neutral axis and rectangular below neutral axis

D. Rectangular above neutral axis and parabolic below neutral axis

What is the correct answer?

4

Sands of zone I are:

A. Course

B. Medium

C. Medium to fine

D. Fine

What is the correct answer?

4

Permissible compressive strength of M 200 concrete grade is

A. 100 kg/cm2

B. 150 kg/cm2

C. 200 kg/cm2

D. 250 kg/cm2

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The bottom and top ends of slump mould are parallel to each other

B. The axis of the mould is perpendicular to the end faces

C. The internal surface of the mould is kept clean and free from set cement

D. The mould is in the form of a frustum of hexagonal pyramid

What is the correct answer?

4

Vicat apparatus is used for

A. Fineness test

B. Consistency test

C. Test for setting time

D. Test for tensile strength

What is the correct answer?

4

Joints in concrete structures, are provided

A. To reduce the tensile stresses likely to be developed due to evaporation of water

B. To minimise the change in the dimensions of the slab

C. To minimise the necessary cracking

D. All the above

What is the correct answer?

4

Which of the following R.C. retaining walls is suitable for heights beyond 6 m?

A. L-shaped wall

B. T-shaped wall

C. Counterfort type

D. All of the above

What is the correct answer?

4

Workability of concrete for a given water content is good if the aggregates, are

A. Rounded aggregate

B. Irregular aggregate

C. Angular aggregate

D. Flaky aggregates

What is the correct answer?

4

Permissible compressive strength of M 200 concrete grade is

A. 100 kg/cm2

B. 150 kg/cm2

C. 200 kg/cm2

D. 250 kg/cm2

What is the correct answer?

4

Wp and Wf are the weights of a cylinder containing partially compacted and fully compacted concrete. If the compaction factor (Wp/Wf) is 0.95, the workability of concrete is

A. Extremely low

B. Very low

C. Low

D. High

What is the correct answer?

4

In the method of voids for determination of the quantity of cement paste, it is assumed that

A. Voids in coarse aggregates are filled by fine aggregates

B. Voids in fine aggregates are filled by the cement paste

C. Volume of fine aggregates is equal to total voids in coarse aggregates plus 10% extra

D. All the above

What is the correct answer?

4

For a slab supported on its four edges with corners held down and loaded uniformly, the Marcus correction factor to the moments obtained by Grashoff Rankine's theory

A. Is always less than 1

B. Is always greater than 1

C. Can be more than 1

D. Can be less than 1

What is the correct answer?

4

The factor which affects workability, is

A. Water content and its temperature

B. Shape and size of the aggregates

C. Air entraining agents

D. All the above

What is the correct answer?

4

Specified compressive strength of concrete is obtained from cube tests at the end of

A. 3 days

B. 7 days

C. 21 days

D. 28 days

What is the correct answer?

4

Pick up the correct statement from the following:

A. Sand obtained from pits, is washed to remove clay and silt

B. Sand obtained from flooded pits, need not be washed before use

C. The chloride in sea shore sand and shingle may cause corrosion of reinforcement if the concrete is porous

D. All the above

What is the correct answer?

4

Under normal conditions using an ordinary cement, the period of removal of the form work, is:

A. 7 days for beam soffits

B. 14 days for bottom slabs of spans 4.6 m and more

C. 21 days for bottom beams over 6 m spans

D. All the above

What is the correct answer?

4

A T-shaped retaining wall mainly consists of

A. One cantilever

B. Two cantilevers

C. Three cantilevers

D. Four cantilevers

What is the correct answer?

4

The risk of segregation is more for

A. Wetter mix

B. Larger proportion of maximum size aggregate

C. Coarser grading

D. All the above

What is the correct answer?

4

Pre-stress loss due to friction occurs

A. Only in post-tensioned beams

B. Only in pre-tensioned beams

C. In both post-tensioned and pre-tensioned beams

D. None of the above

What is the correct answer?

4

For the construction of cement concrete floor, the maximum permissible size of aggregate, is

A. 4 mm

B. 6 mm

C. 8 mm

D. 10 mm

What is the correct answer?

4

The main reason for providing number of reinforcing bars at a support in a simply supported beam is to resist in that zone

A. Compressive stress

B. Shear stress

C. Bond stress

D. Tensile stress