Home
Current Affairs January 2024

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

Correct Answer :

C. Linear programming


Related Questions

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor

What is the correct answer?

4

Pick up the incorrect statement from the following. A critical ratio scheduling

A. Establishes the relative priorities among various activities on a common basis

B. Determines the status of each activity

C. Adjusts automatically changes in activity progress

D. None of the above

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

Which of the following organisations is best suited for steel plants

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line, staff and functional organisations

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction

What is the correct answer?

4

A dummy activity in a net work diagram

A. Is represented by a dotted line

B. Is an artificial activity

C. Does not consume time or resources

D. All of these

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

The main object of scientific layout is

A. To produce better quality of product

B. To utilise maximum floor area

C. To minimise production delays

D. All of these

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Work sampling observations are taken on the basis of

A. Detailed calculations

B. Convenience

C. Table of random numbers

D. Past experience

What is the correct answer?

4

In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

What is the correct answer?

4

The allowed time for a job equals standard time plus

A. Policy allowance

B. Interference allowance

C. Process allowance

D. Learning allowance

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

Gantt chart is used for

A. Inventory control

B. Material handling

C. Production schedule

D. Machine repair schedules

What is the correct answer?

4

What does symbol 'D' imply in work study?

A. Inspection

B. Transport

C. Delay/temporary storage

D. Permanent storage

What is the correct answer?

4

The performance of a specific task in CPM is known as

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

Line organisation is suitable for

A. Sugar industries

B. Oil refining industries

C. Spinning and weaving industries

D. All of these

What is the correct answer?

4

In ABC control policy, maximum attention is given to

A. Those items which consume money

B. Those items which are not readily available

C. Those × items which are in more demand

D. Those items which consume more money

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specification

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All of the above

What is the correct answer?

4

Under the Apprenticeship Act

A. All industries have to necessarily train the apprentices

B. Industries have to train apprentices according to their requirement

C. All industries employing more than 100 workers have to recruit apprentices

D. Only industries employing more than 500 workers have to recruit apprentices

What is the correct answer?

4

In fixed position layout

A. Total production cost is less

B. Material movement is less

C. Capital investment is minimum

D. All of these

What is the correct answer?

4

Which one of the following techniques is used for determining allowances in time study?

A. Acceptance sampling

B. Linear regression

C. Performance rating

D. Work sampling

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event