Breakeven analysis
Value analysis
Linear programming
Queueing theory
C. Linear programming
Hoist
Jib crane
Portable elevator
Chain conveyor
Establishes the relative priorities among various activities on a common basis
Determines the status of each activity
Adjusts automatically changes in activity progress
None of the above
Duration
Total float
Free float
Interfering float
Functional organisation
Line organisation
Staff organisation
Line, staff and functional organisations
Customer satisfaction
Function concept
Profit maximisation
Cost reduction
Is represented by a dotted line
Is an artificial activity
Does not consume time or resources
All of these
Single time estimate
Double time estimate
Triple time estimate
None of these
To produce better quality of product
To utilise maximum floor area
To minimise production delays
All of these
25
50
75
100
Optimistic time
Pessimistic time
Most likely time
All of these
Detailed calculations
Convenience
Table of random numbers
Past experience
Handling and backtracking of materials is too much
Production control is more difficult and costly
Routing and scheduling is more difficult
All of the above
Policy allowance
Interference allowance
Process allowance
Learning allowance
Job production
Batch production
Mass production
Any one of these
Inventory control
Material handling
Production schedule
Machine repair schedules
Inspection
Transport
Delay/temporary storage
Permanent storage
Dummy
Event
Activity
Contract
Determine the critical path
Determine the project completion time
Maintain the required net work
None of these
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with starting of processes
Regulates the progress of job through various processes
Normal time
Slow time
Crash time
Standard time
Sugar industries
Oil refining industries
Spinning and weaving industries
All of these
Those items which consume money
Those items which are not readily available
Those × items which are in more demand
Those items which consume more money
Improving a work method
Improvising a work method
Designing a work method
Reducing inventory costs
Marketing programmes and advertising programmes
Installation of machinery
Research and development of products
All of these
Quality
Statistics
Probability
All of the above
Strict adherence to specification
Separation of planning and design part
Each individual maintains functional efficiency
All of the above
All industries have to necessarily train the apprentices
Industries have to train apprentices according to their requirement
All industries employing more than 100 workers have to recruit apprentices
Only industries employing more than 500 workers have to recruit apprentices
Total production cost is less
Material movement is less
Capital investment is minimum
All of these
Acceptance sampling
Linear regression
Performance rating
Work sampling
An ordinary event
A significant event representing some milestone
An event to be transferred to other network chart
Dangling event