Home
Current Affairs January 2024

What is the correct answer?

4

In a functional organisation

A. Quality of work is better

B. Wastage of material is minimum

C. Specialised knowledge and guidance to individual worker is provided

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

The time taken by a trained worker to perform an operation, while working a steady pace, is known as

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

The important file in making a PERT is

A. An event can't be accomplished until activities leading to it are completed

B. No activity from any event can be started from preceding event till it is completed

C. Length of arrow has nothing to do with time

D. All of the above

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from noncritical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All of the above

What is the correct answer?

4

Which of the following layouts is suited to job production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

The performance of a specific task in CPM is known as

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

In order to avoid excessive multiplication of facilities, the layout preferred is

A. Product layout

B. Process layout

C. Group layout

D. Static layout

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

The employees provident fund act is applicable to

A. All industries

B. All industries other than small and medium industries

C. Volunteers

D. The industries notified by Government

What is the correct answer?

4

'Value' for value engineering and analysis purposes is defined as

A. Purchase value

B. Saleable value

C. Depreciated value

D. Function/cost

What is the correct answer?

4

Which of the following is not wage incentive plan?

A. Differential piece rate system

B. Rowan plan

C. Emerson plan

D. Taylor plan

What is the correct answer?

4

The breakeven point represents

A. The most economical level of operation of any industry

B. The time when unit can run without i loss and profit

C. Time when industry will undergo loss

D. The time when company can make maximum profits

What is the correct answer?

4

Abbreviated work factor data is applied for

A. Material handling operation

B. Maintenance operation

C. Packing and shipping operation

D. All of these

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

CPM is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

In the cost structure of a product, the selling price is determined by the factors such as

A. Sales turn over

B. Lowest competitive price

C. Various elements of the cost

D. All of the above

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

Current assets include

A. Manufacturing plant

B. Manufacturing plant and equipment

C. Inventories

D. Common stock held by the firm

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Pick up the correct statement from the following

A. Programmer evaluation and review technique is event oriented

B. Programmer evaluation and review technique is not event oriented

C. Critical path method is event oriented

D. None of the above

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner