Home
Current Affairs January 2024

What is the correct answer?

4

In a ring beam subjected to uniformly distributed load (i) Shear force at mid span is zero (ii) Shear force at mid span is maximum (iii) Torsion at mid span is zero (iv) Torsion at mid span is maximum The correct answer is

A. (i) and (iii)

B. (i) and (iv)

C. (ii) and (iii)

D. (ii) and (iv)

Correct Answer :

A. (i) and (iii)


Related Questions

What is the correct answer?

4

Permissible compressive strength of M 150 concrete grade is

A. 100 kg/cm2

B. 150 kg/cm2

C. 200 kg/cm2

D. 250 kg/cm2

What is the correct answer?

4

Modulus of elasticity of steel as per IS: 4561978 shall be taken as

A. 20 kN/cm²

B. 200 kN/cm²

C. 200 kN/mm²

D. 2 × 106 N/cm²

What is the correct answer?

4

Normally pre-stressing wires are arranged in the

A. Upper part of the beam

B. Lower part of the beam

C. Center

D. Anywhere

What is the correct answer?

4

The percentage of reinforcement in case of slabs, when high strength deformed bars are used is not less than

A. 0.15

B. 0.12

C. 0.30

D. 1.00

What is the correct answer?

4

The surface where two successive placements of concrete meet, is known as

A. Contraction joint

B. Expansion joint

C. Construction joint

D. Both (a) and (b)

What is the correct answer?

4

The rock which is not calcareous, is:

A. Lime stone

B. Chalk

C. Laterite

D. None of these

What is the correct answer?

4

Ordinary Portland cement is manufactured from

A. Lime stone and clay

B. Gypsum and lime

C. Pozzolana

D. Lime, pozzolana and clay

What is the correct answer?

4

Pick up the correct statement from the following:

A. Construction joints are necessarily planned for their locations

B. Expansion joints are provided to accommodate thermal expansion

C. Construction joints are provided to control shrinkage cracks

D. All the above

What is the correct answer?

4

In case of hand mixing of concrete, the extra cement to be added is

A. 5 %

B. 10 %

C. 15 %

D. 20 %

What is the correct answer?

4

Ordinary concrete is not used for concrete grade

A. M 100

B. M 150

C. M 250

D. M 400

What is the correct answer?

4

In a ring beam subjected to uniformly distributed load (i) Shear force at mid span is zero (ii) Shear force at mid span is maximum (iii) Torsion at mid span is zero (iv) Torsion at mid span is maximum The correct answer is

A. (i) and (iii)

B. (i) and (iv)

C. (ii) and (iii)

D. (ii) and (iv)

What is the correct answer?

4

Separation of coarse aggregates from mortar during transportation, is known

A. Bleeding

B. Creeping

C. Segregation

D. Shrinkage

What is the correct answer?

4

The grade of concrete M 150 means that compressive strength of a 15 cm cube after 28 days, is

A. 100 kg/cm2

B. 150 kg/cm2

C. 200 kg/cm2

D. 250 kg/cm2

What is the correct answer?

4

In T-shaped R C. retaining walls, the main reinforcement in the stem is provided on

A. The front face in one direction

B. The front face in both directions

C. The inner face in one direction

D. The inner face in both directions

What is the correct answer?

4

If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is,

A. 20 %

B. 25 %

C. 30 %

D. 35 %

What is the correct answer?

4

Higher workability of concrete is required if the structure is

A. Made with cement concrete

B. Thick and reinforced

C. Thin and heavily reinforced

D. Thick and heavily reinforced

What is the correct answer?

4

The approximate value of the ratio between direct tensile strength and flexural strength is

A. 0.33

B. 0.5

C. 0.75

D. 1.0

What is the correct answer?

4

Pick up the correct statement from the following:

A. Lime in excess, causes the cement to expand and disintegrate

B. Silica in excess, causes the cement to set slowly

C. Alumina in excess, reduces the strength of the cement

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. Calcium chloride acts as a retarder

B. Calcium chloride acts as an accelerator

C. Gypsum (calcium sulphate) acts as a retarder

D. Both (b) and (c)

What is the correct answer?

4

The increased cohesiveness of concrete, makes it

A. Less liable to segregation

B. More liable to segregation

C. More liable to bleeding

D. More liable for surface scaling in frosty weather

What is the correct answer?

4

For a good concrete

A. Aggregates should be hard and durable

B. Water should be free from organic materials

C. Cement should be sufficient to produce the required strength

D. All the above

What is the correct answer?

4

For the construction of cement concrete dams, the maximum permissible size of the aggregates, is

A. 40 mm

B. 50 mm

C. 60 mm

D. 70 mm

What is the correct answer?

4

Joints in concrete structures, are provided

A. To reduce the tensile stresses likely to be developed due to evaporation of water

B. To minimise the change in the dimensions of the slab

C. To minimise the necessary cracking

D. All the above

What is the correct answer?

4

Setting time of cement increases by adding

A. Gypsum

B. Hydrogen peroxide

C. Calcium chloride

D. Sodium oxide

What is the correct answer?

4

For the construction of R.C.C. slabs, columns, beams, walls, etc. the grade of concrete mix used, is

A. 1 : 3 : 6

B. 1 : 1 ½ : 3

C. 1 : 2 : 4

D. 1 : 1 : 2

What is the correct answer?

4

If a grading curve is horizontal between the portions of 20 mm I.S. Sieve and 4.75 mm I.S. Sieve, the graded aggregates do not contain

A. 20 mm particles

B. 10 mm particles

C. 4.75 mm particles

D. All the above

What is the correct answer?

4

The size of fine aggregates does not exceed

A. 2.75 mm

B. 3.00 mm

C. 3.75 mm

D. 4.75 mm

What is the correct answer?

4

The compressive strength of 100 mm cube as compared to 150 mm cube is always

A. Less

B. More

C. Equal

D. None of the above

What is the correct answer?

4

If the size of panel in a flat slab is 6 m × 6 m, then as per Indian Standard Code, the widths of column strip and middle strip are

A. 3.0 m and 1.5 m

B. 1.5 m and 3.0 m

C. 3.0 m and 3.0 m

D. 1.5 m and 1.5 m

What is the correct answer?

4

In pre-stressed concrete

A. Forces of tension and compression change but lever arm remains unchanged

B. Forces of tension and compressions remain unchanged but lever arm changes with the moment

C. Both forces of tension and compression as well as lever arm change

D. Both forces of tension and compression as well as lever arm remain unchanged