In CPM, the cost slope is determined by

A. Crash cost/Normal Cost

B. (Crash Cost - Normal cost)/ (Normal time - Crash time)

C. Normal Cost/Crash cost

D. (Normal cost - Crash cost)/ (Normal time - Crash time)

Please do not use chat terms. Example: avoid using "grt" instead of "great".

You can do it
  1. The main disadvantage of line organisation is
  2. Which of the following layouts is suited to job production?
  3. Product layout is employed for
  4. Work study involves
  5. Motion study involves analysis of
  6. PERT has following time estimate
  7. The simplex method is the basic method for
  8. PERT
  9. Routing assists engineers in deciding in advance
  10. The bonus increases in proportion to the increase in efficiency. This statement applies to
  11. A feasible solution to the linear programming problem should
  12. In order to avoid excessive multiplication of facilities, the layout preferred is
  13. Which of the following are the principles of material handling?
  14. The term 'value' in value engineering refers to
  15. In ABC control policy, maximum attention is given to
  16. For material transportation, conveyors are used when the prevailing conditions include
  17. In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
  18. String diagram is used when
  19. The basic difference between PERT and CPM is that
  20. Military organisation is known as
  21. When slack of an activity is negative
  22. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
  23. The type of layout used for manufacturing steam turbines, is
  24. Dummy activities are used to
  25. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations…
  26. Standard time is defined as
  27. The technique for establishing and maintaining priorities among the various jobs of any project is known…
  28. Scheduling
  29. Pick up the correct statement from the following
  30. One of the basic essentials of an incentive plan is that