Home
Current Affairs January 2024

What is the correct answer?

4

In break even analysis, total cost consists of

A. Fixed cost + sales revenue

B. Variable cost + sales revenue

C. Fixed cost + variable cost

D. Fixed cost + variable cost + profit

Correct Answer :

C. Fixed cost + variable cost


Related Questions

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

For handling materials during manufacture of cement, a _________ is widely used.

A. Belt conveyor

B. Bucket conveyor

C. Fork lift truck

D. Overhead crane

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Inventory management consists of

A. Effective running of stores

B. State of merchandise methods of storing and maintenance etc.

C. Stock control system

D. All of the above

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Scanlon Plan

B. Rowan Plan

C. Taylor Differential Piece Rate System

D. Halsey Premium Plan

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

The critical path of a network represents

A. The minimum time required for completion of project

B. The maximum time required for completion of project

C. Maximum cost required for completion of project

D. Minimum cost required for completion of project

What is the correct answer?

4

Material handling and plant location is analysed by

A. Gantt chart

B. Bin chart

C. Emerson chart

D. Travel chart

What is the correct answer?

4

Queueing theory deals with problems of

A. Material handling

B. Reducing the waiting time or idle time

C. Better utilization of man services

D. Effective use of machines

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

The purpose of micro-motion study is to

A. Assist in finding out the most efficient way of doing work

B. Train the individual operator regarding the motion economy principles

C. Help in collecting the motion time data for synthetic time standards

D. All of the above

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

PERT requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

The aim of value engineering is to

A. Find the depreciation value of a machine

B. Determine the selling price of a product

C. Minimise the cost without change in quality of the product

D. All of the above

What is the correct answer?

4

Gantt chart provides information about the

A. Material handling

B. Proper utilisation of manpower

C. Production schedule

D. Efficient working of machine

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

What is the correct answer?

4

Which of the following statement is correct?

A. When slack of an activity is zero, it falls only on critical path.

B. CPM technique is useful to minimise the direct and indirect expenses.

C. Critical path of a net work represents the minimum time required for completion of project.

D. All of the above

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

Simplex method is the method used for

A. Value analysis

B. Network analysis

C. Linear programming

D. Queuing theory

What is the correct answer?

4

Linear programming can be applied successfully to

A. Chemical industry

B. Oil industry

C. Banks

D. All of these

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

The reasons which are basically responsible for the formation of a queue should be that

A. The average service rate Hess than the average arrival rate

B. Output rate is linearly proportional to input

C. Output rate is constant and the input varies in a random manner

D. All of the above