Handling and backtracking of materials is too much
Production control is more difficult and costly
Routing and scheduling is more difficult
All of the above
D. All of the above
Analyse material handling
Determine inventory control difficulties
Plan material handling procedure and routes
All of the above
Where production activities are involved
In judging the rating of machines
In improving industrial relations
In judging the output of a man and improving it
Dispatch of sales order
Dispatch of factory mail
Dispatch of finished product of the user
Dispatch of work orders through shop floor
Event
Free float
Artificial
Dummy
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
An analytic tool in concept
Limit up of event oriented diagrams
Used for research and development projects
All of the above
Lowers overall manufacturing time
Requires less space for placing machines
Utilises machine and labour better
All of these
Sales
Inspection time
Waiting time
Production time
Relative values of a job
Workers performance on a job
Worth of a machine
Value of overall production
Bar chart method
Milestone chart
Critical path method (CPM)
Programme evaluation and review technique (PERT)
Process layout
Product layout
Fixed position layout
Plant layout
Batch production
Continuous production
Effective utilization of machine
All of the above
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with the starting of processes
Regulates the progress of job through various processes
8
12
16
20
AP/C
2AP/C
√(AP/C)
(AP/C)2
To concentrate his attention on critical activities
To divert the resources from noncritical advanced activities to critical activities
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
All of the above
Fixed cost line
Variable cost line
Total cost line
Sales revenue line
The maximum time which an activity might require
The average time required for a job
The most probable time considering all conditions
The minimum time in which an activity can possibly be accomplished
Jobbing work economics are involved
Production is on large scale
Only few components are involved
Costly equipment is used
EF = ES + D
LS = LFD
LF = LS + D
All of the above
Sinking fund method
Straight line method
ABC charging method
Annuity charging method
Latest start time of succeeding event earliest finish time of preceding event activity time
Latest start time of the event earliest start time of the event
Latest finish time of event earliest finish time of the event
Anyone of the above
Breakeven analysis
Value analysis
Linear programming
Queueing theory
Method study and work measurement
Method study and time study
Time study and work measurement
Method study and job evaluation
Highly skilled workers are needed
Unit costs are high
Operations are labour-intensive
All of these
A standard rating system
A merit rating system
A job evaluation system
His individual performance
Operation
Inspection
Delay/ temporary Storage
Permanent storage
Fixed cost
Variable cost
Fixed and variable costs
Operation costs
Iron and steel
Food processing
Oil and chemical
All of the above
Those items which consume money
Those items which are not readily available
Those × items which are in more demand
Those items which consume more money