Home
Current Affairs January 2024

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. CPS (Critical Path Scheduling)

D. All of the above

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Inventory management consists of

A. Effective running of stores

B. State of merchandise methods of storing and maintenance etc.

C. Stock control system

D. All of the above

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

The factors which are to be considered while developing a good wage incentive plan will include

A. Adequate incentive

B. Ease of administration

C. Guaranteed basic pay

D. All of these

What is the correct answer?

4

Slack represents the difference between the

A. Latest allowable time and the normal expected time

B. Latest allowable time and the earliest expected time

C. Proposed allowable time and the earliest expected time

D. Normal allowable time and the latest expected time

What is the correct answer?

4

The purpose of micro-motion study is to

A. Assist in finding out the most efficient way of doing work

B. Train the individual operator regarding the motion economy principles

C. Help in collecting the motion time data for synthetic time standards

D. All of the above

What is the correct answer?

4

Direct expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. None of these

What is the correct answer?

4

Which of the following layouts is suited to job production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

In Halsey 50-50 plan, output standards are established

A. By time study

B. From previous production records

C. From one's judgement

D. All of the above

What is the correct answer?

4

'Value' for value engineering and analysis purposes is defined as

A. Purchase value

B. Saleable value

C. Depreciated value

D. Function/cost

What is the correct answer?

4

Line organisation is suitable for

A. Sugar industries

B. Oil refining industries

C. Spinning and weaving industries

D. All of these

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

What is the correct answer?

4

Gantt chart is used for

A. Inventory control

B. Material handling

C. Production schedule

D. Machine repair schedules

What is the correct answer?

4

Pick up the correct statement from the following

A. Critical path method is an improvement upon bar chart method

B. Critical path method provides a realistic approach to the daily problems

C. Critical path method avoids delays which are very common in bar chart

D. All of the above

What is the correct answer?

4

ABC analysis deals with

A. Analysis of process chart

B. Flow of material

C. Ordering schedule of job

D. Controlling inventory costs money

What is the correct answer?

4

Which of the following charts are used for plant layout design?

A. Operation process chart

B. Man machine chart

C. Travel chart

D. All of these

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Emergency rush order can be pushed more effectively in

A. Job production

B. Automatic production

C. Continuous production

D. Intermittent production

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

What is the correct answer?

4

The type of organisation preferred for an automobile industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The main object of scientific layout is

A. To produce better quality of product

B. To utilise maximum floor area

C. To minimise production delays

D. All of these

What is the correct answer?

4

A systematic job improvement sequence will consist of

A. Motion study

B. Time study

C. Job enrichment

D. All of these

What is the correct answer?

4

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth

B. One-half

C. Equal to

D. Twice

What is the correct answer?

4

Routing assists engineers in deciding in advance

A. The flow of material in the plant

B. The methods of proper utilization of manpower

C. The methods of proper utilization of machines

D. The layout of factory facilities

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction