Home
Current Affairs January 2024

What is the correct answer?

4

In the method of tube boring of soil investigation, the following is essential:

A. A tube of about 2 metres length and 20 cm diameter with a cutting edge

B. A flap valve at the bottom of tube is provided to extract the soil sample

C. The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

The inner section of a cavity wall, is generally known as

A. Buttress

B. Leaf wall

C. Pilaster

D. Pillar

What is the correct answer?

4

The Auger boring method is not suitable for

A. Very hard soil

B. Cemented soil

C. Vary soft soil

D. All the above

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In dog-legged stairs, no space between its flights is provided

B. In open newel stair, a rectangular well is provided

C. In geometric stair, a curved shaped well between forward and backward flights, is provided

D. In geometrical stair, two quarter space landing is provided

What is the correct answer?

4

The rock formed from the solidification of molten matter (magma) is called:

A. Sedimentary rock

B. Metamorphic rock

C. Igneous rock

D. None of the above

What is the correct answer?

4

The ceiling height of a building is

A. Between ceiling and ground level

B. Between ceiling and floor level

C. Upto roof above ground level

D. Upto ceiling from the ground level

What is the correct answer?

4

To stagger vertical joints in successive courses of a wall, a piece of brick is generally used at the end of the course, which is known as

A. Bat

B. Header

C. Stretcher

D. Closer

What is the correct answer?

4

In which of the following pairs both trees yield soft wood?

A. Deodar and Shishum

B. Chir and sal

C. Sal and teak

D. Chir and deodar

What is the correct answer?

4

For the construction of flyovers in sandy soils, the type of foundation provided, is

A. Strap footing

B. Raft footing

C. Combined footing

D. Pier footing

What is the correct answer?

4

The process of working a flat for the finishing coat, is known

A. Dubbing out

B. Floating

C. Knitting

D. Blistering

What is the correct answer?

4

The construction joints in buildings are provided after

A. 10 m

B. 15 m

C. 20 m

D. 40 m

What is the correct answer?

4

Pick up the correct statement from the following:

A. Isolated footing is provided under column to transfer the load safely to soil bed

B. Column footings may have steps or projections in the concrete base

C. Heavily loaded column base must be provided steel reinforcement in both directions

D. All the above

What is the correct answer?

4

Pile foundations are suitable for

A. Water logged soils

B. Soft rocks

C. Compact soils

D. Multi-storeyed buildings

What is the correct answer?

4

Weep holes are provided in retaining and breast walls

A. To drain off the water from the filling

B. To ventilate the stone masonry

C. To add architectural beauty

D. To increase compaction of the earth retained

What is the correct answer?

4

Pick up the correct statements from the following:

A. Cracks appear on the plastered surface in the form of hair cracks

B. In brick work, the efflorescence is removed by applying a solution of zinc sulphate and water

C. Excessive thermal variations in the backing or plaster causes the plaster to fall

D. All the above

What is the correct answer?

4

For providing a raft foundation, the following activities are involved
1. Ramming the foundation bed
2. Excavation of the soil upto required depth
3. Laying the reinforcement over the foundation bed
4. Curing the cement concrete placed over reinforcement
5. Pouring the cement concrete over the reinforcement The correct sequence is

A. 1, 2, 3, 4, 5

B. 5, 4, 3, 2, 1

C. 2, 1, 3, 5, 4

D. 3, 2, 5, 1, 4

What is the correct answer?

4

The inclined support at the ends of treads and rises of a stair, is known as

A. Baluster

B. Header

C. String

D. Beam

What is the correct answer?

4

Couple roof is used for spans

A. 3.5 m or less

B. 3.5 m but less than 5 m

C. 5 m but less than 6.5 m

D. 6.5 m but less than 8 m

What is the correct answer?

4

The form Work including the props can be removed from beams, only after

A. 3 day

B. 7 days

C. 14 days

D. 21 days

What is the correct answer?

4

The arrangement of supporting an existing structure by providing supports underneath, is known as

A. Shoring

B. Underpinning

C. Jacking

D. Piling

What is the correct answer?

4

Which of the following metal sheets is most effective in preventing dampness?

A. Copper sheets

B. Lead sheets

C. Aluminium sheets

D. All the above

What is the correct answer?

4

Ornamental moulded course placed on the top of a wall, is

A. Cornice

B. Coping

C. Frieze

D. Lintel

What is the correct answer?

4

To ensure that supporting area of an offset footing of a boundary wall is fully compressive, the C.G. of load must act

A. At the centre of the base

B. Within the middle third of the base

C. Within the middle fifth of the base

D. Neither (a), (b) nor (c)

What is the correct answer?

4

The depth of the ground water table may be ascertained by

A. Looking through the well in the vicinity

B. Standing on the well in the vicinity

C. Measuring the depth of water in the well

D. None of the above

What is the correct answer?

4

In a colar beam roof

A. There is no horizontal tie beam

B. There is a horizontal tie at the feet of rafters only

C. There is a horizontal tie at almost the middle of rafters only

D. There are two horizontal ties, one at the feet and other at the middle of the rafters

What is the correct answer?

4

The alignment of a cross joint along the plumb line is

A. Bed block

B. Perpend

C. Lintel

D. Vertical line

What is the correct answer?

4

Pick up the correct statement from the following:

A. The pile driven in sand is called sand pile

B. The drilled hole filled with sand is called sand pile

C. The sand piles are used for bearing purposes

D. None of these

What is the correct answer?

4

Bearing capacity of soils cannot be improved by

A. Draining sub-soil water

B. Ramming crushed stone in soil

C. Driving sand piles

D. Watering surface of soil

What is the correct answer?

4

A wall constructed to resist the pressure of an earth filling, is called

A. Retaining wall

B. Breast wall

C. Buttress

D. Parapet wall

What is the correct answer?

4

The type of pile which is driven at an inclination to resist inclined forces is known as

A. Friction pile

B. Sheet pile

C. Batter pile

D. Anchor pile

What is the correct answer?

4

The disease of dry rot in timber is caused by

A. Lack of ventilation

B. Alternate wet and dry conditions

C. Complete submergence in water

D. None of the above