Home
Current Affairs January 2024

What is the correct answer?

4

In the perpetual inventory control, the material is checked when it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Alarming value

Correct Answer :

A. Minimum value


Related Questions

What is the correct answer?

4

Gantt charts provide information about

A. Breakeven point analysis

B. Production schedule

C. Material handling layout

D. Determining selling price

What is the correct answer?

4

The deductions for, employees provident fund start

A. Immediately on joining the service

B. After 60 days of joining the service

C. After 100 days of joining the service

D. After 240 days of joining the service

What is the correct answer?

4

For a product layout the material handling equipment must

A. Have full flexibility

B. Employ conveyor belts, trucks, tractors etc.

C. Be a general purpose type

D. Be designed as special purpose for a particular application

What is the correct answer?

4

In order that linear programming techniques provide valid results

A. Relations between factors must be linear (positive)

B. Relations between factors must be linear (negative)

C. Either (A) or (B)

D. Only one factor should change at a time, others remaining constant

What is the correct answer?

4

String diagram is used when

A. Team of workers is working at a place

B. Material handling is to be done

C. Idle time is to be reduced

D. All of the above

What is the correct answer?

4

The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as

A. Job enlargement

B. Job enrichment

C. Job rotation

D. Job evaluation

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

Travel charts are used to

A. Analyse material handling

B. Determine inventory control difficulties

C. Plan material handling procedure and routes

D. All of the above

What is the correct answer?

4

Breakeven analysis is a

A. Short term analysis

B. Long term analysis

C. Average of short and long term analysis

D. Any one of these

What is the correct answer?

4

The value engineering technique in which experts of the same rank assemble for product development is called

A. Delphi

B. Brain storming

C. Morphological analysis

D. Direct expert comparison

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

The product layout

A. Lowers overall manufacturing time

B. Requires less space for placing machines

C. Utilises machine and labour better

D. All of these

What is the correct answer?

4

A-B-C analysis

A. Is a basic technique of materials management

B. Is meant for relative inventory control

C. Does not depend upon the unit cost of the item but on its annual consumption

D. All of the above

What is the correct answer?

4

The start or completion of task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

According to Rowan plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

What is the correct answer?

4

Work study is done with the help of

A. Process chart

B. Material handling

C. Stop watch

D. All of the above

What is the correct answer?

4

The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as

A. Event

B. Free float

C. Artificial

D. Dummy

What is the correct answer?

4

Father of time study was

A. F.W. Taylor

B. H.L. Gantt

C. F.B. Gilbert

D. R.M. Barnes

What is the correct answer?

4

Pick up the incorrect statement from the following. A critical ratio scheduling

A. Establishes the relative priorities among various activities on a common basis

B. Determines the status of each activity

C. Adjusts automatically changes in activity progress

D. None of the above

What is the correct answer?

4

The main objective of work measurement is to

A. Plan and schedule of production

B. Formulate a proper incentive scheme

C. Estimate the selling prices and delivery dates

D. All of the above

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95

What is the correct answer?

4

Queueing theory is used for

A. Inventory problems

B. Traffic congestion studies

C. Job-shop scheduling

D. All of the above

What is the correct answer?

4

In Halsey 50-50 plan, output standards are established

A. By time study

B. From previous production records

C. From one's judgement

D. All of the above

What is the correct answer?

4

Valve analysis is particularly of interest when

A. Jobbing work economics are involved

B. Production is on large scale

C. Only few components are involved

D. Costly equipment is used

What is the correct answer?

4

Pick up the incorrect statement from the following

A. An activity of the project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn (to scale from) left to right

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan