Home
Current Affairs January 2024

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above

Correct Answer :

A. Overhead crane


Related Questions

What is the correct answer?

4

Micro-motion study is

A. Analysis of one stage of motion chart

B. Motion study, when seen on a time chart

C. Subdivision of an operation into therbligs and their analysis

D. Enlarged view of motion study

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

The routing function in a production system design is concerned with

A. Manpower utilisation

B. Quality assurance of the product

C. Machine utilisation

D. Optimising material flow through the plant

What is the correct answer?

4

Queueing theory is used for

A. Inventory problems

B. Traffic congestion studies

C. Job-shop scheduling

D. All of the above

What is the correct answer?

4

P.M.T.S. (Predetermined Motion Time Systems) include

A. M.T.M. (Method Time Measurement)

B. W.F.S. (Work Factor Systems)

C. B.M.T.S. (Basic Motion Time Study)

D. All of these

What is the correct answer?

4

Pick up the correct statement about relationship between various floats

A. Free float = total float

B. Independent float = total float

C. Independent float > free float

D. Independent float < free float

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

Which of the following charts are used for plant layout design?

A. Operation process chart

B. Man machine chart

C. Travel chart

D. All of these

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

In inventory control, the economic order quantity is the

A. Optimum lot size

B. Highest level of inventory

C. Lot corresponding to breakeven point

D. Capability of a plant to produce

What is the correct answer?

4

CPM is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

The mathematical technique for finding the best use of limited resources in an optimum manner is known as

A. Operation research

B. Linear programming

C. Network analysis

D. Breakeven analysis

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

In a PERT chart

A. All activities should be numbered

B. Only important activities should be numbered

C. Only critical activities are numbered

D. Only selected activities are numbered

What is the correct answer?

4

In the Halsey system of wage incentive plan, a worker is

A. Paid as per efficiency

B. Ensured of minimum wages

C. Not paid any bonus till his efficiency

D. Never a loser

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

Break-even analysis consists of

A. Fixed expenses

B. Variable cost

C. Sales revenue

D. All of these

What is the correct answer?

4

Performance rating is equal to

A. Observed performance + normal performance

B. Observed performance - normal performance

C. Observed performance × normal performance

D. None of the above

What is the correct answer?

4

Abbreviated work factor data is applied for

A. Material handling operation

B. Maintenance operation

C. Packing and shipping operation

D. All of these

What is the correct answer?

4

The main object of scientific layout is

A. To produce better quality of product

B. To utilise maximum floor area

C. To minimise production delays

D. All of these

What is the correct answer?

4

Standard time as compared to normal time is

A. Greater

B. Smaller

C. Equal

D. There is no such correlation