Home
Current Affairs January 2024

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

Correct Answer :

B. Workers performance on a job


Related Questions

What is the correct answer?

4

Standing orders which are statutory are applicable to

A. All industries

B. All process industries and thermal power plants

C. Only major industries

D. All industries employing more than 100 workers

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

In order that linear programming techniques provide valid results

A. Relations between factors must be linear (positive)

B. Relations between factors must be linear (negative)

C. Either (A) or (B)

D. Only one factor should change at a time, others remaining constant

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

String diagram is used when

A. Team of workers is working at a place

B. Material handling is to be done

C. Idle time is to be reduced

D. All of the above

What is the correct answer?

4

PERT has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Works cost implies

A. Primary cost

B. Factory cost

C. Factory expenses

D. Primary cost + factory expenses

What is the correct answer?

4

Critical path moves along the activities having total float of

A. Positive value

B. Negative value

C. Zero value

D. Same value

What is the correct answer?

4

In jobbing production

A. Highly skilled workers are needed

B. Unit costs are high

C. Operations are labour-intensive

D. All of these

What is the correct answer?

4

The performance of a specific task in CPM is known as

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

Work study involves

A. Only method study

B. Only work measurement

C. Method study and work measurement

D. Only motion study

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

The mathematical technique for finding the best use of limited resources in an optimum manner is known as

A. Operation research

B. Linear programming

C. Network analysis

D. Breakeven analysis

What is the correct answer?

4

Micro-motion study is

A. Enlarged view of motion study

B. Analysis of one stage of motion study

C. Minute and detailed motion study

D. Subdivision of an operation into therbligs and their analysis

What is the correct answer?

4

The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as

A. Job enlargement

B. Job enrichment

C. Job rotation

D. Job evaluation

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of the above

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Expediting function consists in keeping a watch on

A. Operator's activity

B. Flow of material and in case of trouble locate source of trouble

C. Minimising the delays

D. Making efficient despatching