100 hrs
122 hrs
177 hrs
112 hrs
D. 112 hrs
Work done by the two pipes in 1 hour =(1/14)+(1/16)=(15/112).
Time taken by these pipes to fill the tank = (112/15) hrs = 7 hrs 28 min.
Due to leakage, time taken = 7 hrs 28 min + 32 min = 8 hrs
Work done by (two pipes + leak) in 1 hour = (1/8).
Work done by the leak m 1 hour =(15/112)-(1/8)=(1/112).
Leak will empty the full cistern in 112 hours.