Home
Current Affairs January 2024

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

Correct Answer :

A. Work sampling


Related Questions

What is the correct answer?

4

Simplex method is the method used for

A. Value analysis

B. Network analysis

C. Linear programming

D. Queuing theory

What is the correct answer?

4

Work study is done with the help of

A. Process chart

B. Material handling

C. Stop watch

D. All of the above

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

Positive slack on a PERT indicates that project is

A. Ahead of schedule

B. Beyond schedule

C. As per schedule

D. On critical path

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above

What is the correct answer?

4

Break-even analysis can be used for

A. Short run analysis

B. Long run analysis

C. Average of above two run analysis

D. There is no such criterion

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor

What is the correct answer?

4

The start or completion of task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

Work study is most useful

A. Where production activities are involved

B. In judging the rating of machines

C. In improving industrial relations

D. In judging the output of a man and improving it

What is the correct answer?

4

Time study is carried out

A. By finding all the significant informations regarding the job, work place and machine tool etc.

B. By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

C. By observing and recording the time taken by the operator for an operation

D. All of the above

What is the correct answer?

4

PERT is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

In ABC control policy, maximum attention is given to

A. Those items which consume money

B. Those items which are not readily available

C. Those × items which are in more demand

D. Those items which consume more money

What is the correct answer?

4

In CPM, the cost slope is determined by

A. Crash cost/Normal Cost

B. (Crash Cost - Normal cost)/ (Normal time - Crash time)

C. Normal Cost/Crash cost

D. (Normal cost - Crash cost)/ (Normal time - Crash time)

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

An event is indicated on the network by

A. A straight line

B. A number enclosed in a circle or a square

C. A straight line with circles at the ends

D. A dotted line

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

Gantt charts provide information about

A. Breakeven point analysis

B. Production schedule

C. Material handling layout

D. Determining selling price

What is the correct answer?

4

Break-even analysis consists of

A. Fixed expenses

B. Variable cost

C. Sales revenue

D. All of these

What is the correct answer?

4

PERT and CPM are

A. Techniques to determine project status

B. Decision making techniques

C. Charts which increase aesthetic appearance of rooms

D. Aids to the decision maker

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack

What is the correct answer?

4

Which of the following layouts is suited for mass production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view

B. Motion study observed on enhanced time intervals

C. Motion study of a sequence of operations conducted systematically

D. Study of man and machine conducted simultaneously

What is the correct answer?

4

In breakeven analysis, total cost consists of

A. Fixed cost

B. Variable cost

C. Fixed cost + variable cost

D. Fixed cost + variable cost + overheads

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

In order to avoid excessive multiplication of facilities, the layout preferred is

A. Product layout

B. Process layout

C. Group layout

D. Static layout