Home
Current Affairs January 2024

What is the correct answer?

4

PERT/CPM, techniques can be used for following applications

A. Once through project

B. Maintenance jobs

C. Research and development

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

The main advantage of line organisation is its

A. Effective command and control

B. Defined responsibilities at all levels

C. Rigid discipline in the organisation

D. All of the above

What is the correct answer?

4

Actual performance of a task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. Average float

What is the correct answer?

4

'Value' for value engineering and analysis purposes is defined as

A. Purchase value

B. Saleable value

C. Depreciated value

D. Function/cost

What is the correct answer?

4

The main objective of work measurement is to

A. Plan and schedule of production

B. Formulate a proper incentive scheme

C. Estimate the selling prices and delivery dates

D. All of the above

What is the correct answer?

4

Emergency rush order can be pushed more effectively in

A. Job production

B. Automatic production

C. Continuous production

D. Intermittent production

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

What is the correct answer?

4

PERT requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

Work study comprises following main techniques

A. Method study and work measurement

B. Method study and time study

C. Time study and work measurement

D. Method study and job evaluation

What is the correct answer?

4

In the cost structure of a product, the selling price is determined by the factors such as

A. Sales turn over

B. Lowest competitive price

C. Various elements of the cost

D. All of the above

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

Service time in queuing theory is usually assumed to follow

A. Normal distribution

B. Poissons distribution

C. Erlang distribution

D. Exponential law

What is the correct answer?

4

Which of the following equations is not in conformity with others?

A. Organisation performance × motivation = profits

B. Knowledge × skill = ability

C. Ability × motivation = performance

D. Attitude × situation = motivation

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

Pessimistic time is

A. The maximum time which an activity might require

B. The average time required for a job

C. The most probable time considering all conditions

D. The minimum time in which an activity can possibly be accomplished

What is the correct answer?

4

Fixed position layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of

A. Product layout

B. Process layout

C. Fixed position layout

D. A combination of line and process layout

What is the correct answer?

4

Pick up the incorrect statement from the following. A critical ratio scheduling

A. Establishes the relative priorities among various activities on a common basis

B. Determines the status of each activity

C. Adjusts automatically changes in activity progress

D. None of the above

What is the correct answer?

4

The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)

A. (to + tp + tn)/3

B. (to + 2tp + tn)/4

C. (to + 4tp + tn)/5

D. (to + tp + 4tn)/6

What is the correct answer?

4

Which of the following type of layout is suitable for automobile manufacturing concern?

A. Product layout

B. Process layout

C. Fixed position layout

D. Combination layout

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

Under the Apprenticeship Act

A. All industries have to necessarily train the apprentices

B. Industries have to train apprentices according to their requirement

C. All industries employing more than 100 workers have to recruit apprentices

D. Only industries employing more than 500 workers have to recruit apprentices

What is the correct answer?

4

In fixed position layout

A. Total production cost is less

B. Material movement is less

C. Capital investment is minimum

D. All of these

What is the correct answer?

4

Choose the wrong statement Time study is used to

A. Determine overhead expenses

B. Provide a basis for setting piece prices or incentive wages

C. Determine standard costs

D. Determine the capability of an operator to handle the number of machines

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programmes

C. Is used for repetitive works

D. All of the above

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes