Home
Current Affairs January 2024

What is the correct answer?

4

PERT requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

Correct Answer :

C. Triple time estimate


Related Questions

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. Average float

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

What is the correct answer?

4

Halsey plan of wage incentive

A. Is not applied to all level of workers

B. Is applied to all level of workers

C. Does not guarantee minimum wage

D. Is based upon efficiency of worker

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

In A-B-C analysis, which class of items are generally large in number?

A. A

B. B

C. C

D. None of these

What is the correct answer?

4

Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

What is the correct answer?

4

Value engineering aims at finding out the

A. Depreciation value of a product

B. Resale value of a product

C. Major function of the item and accomplishing the same at least cost without change in quality

D. Breakeven point when machine requires change

What is the correct answer?

4

In micro-motion study, therblig is described by

A. A symbol

B. An event

C. An activity

D. Standard symbol and colour

What is the correct answer?

4

In the perpetual inventory control, the material is checked when it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Alarming value

What is the correct answer?

4

Pick up the correct statement about relationship between various floats

A. Free float = total float

B. Independent float = total float

C. Independent float > free float

D. Independent float < free float

What is the correct answer?

4

Father of time study was

A. F.W. Taylor

B. H.L. Gantt

C. F.B. Gilbert

D. R.M. Barnes

What is the correct answer?

4

The product layout

A. Lowers overall manufacturing time

B. Requires less space for placing machines

C. Utilises machine and labour better

D. All of these

What is the correct answer?

4

The process layout is best suited where

A. Specialisation exists

B. Machines are arranged according to sequence of operation

C. Few number of non-standardised units is to be produced

D. Mass production is envisaged

What is the correct answer?

4

A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Which of the following charts are used for plant layout design?

A. Operation process chart

B. Man machine chart

C. Travel chart

D. All of these

What is the correct answer?

4

If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then breakeven point is equal to

A. (F × V)/P

B. (F × P)/V

C. F/[1 + (V/P)]

D. F/[1 - (V/P)]

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

What is the correct answer?

4

Pessimistic time is

A. The maximum time which an activity might require

B. The average time required for a job

C. The most probable time considering all conditions

D. The minimum time in which an activity can possibly be accomplished

What is the correct answer?

4

In inventory control, the economic order quantity is the

A. Optimum lot size

B. Highest level of inventory

C. Lot corresponding to breakeven point

D. Capability of a plant to produce

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of any project is known as

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

The chart which gives an estimate about the amount of materials handling between various work stations is known as

A. Flow chart

B. Process chart

C. Travel chart

D. Operation chart

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

The factors to be considered for production scheduling are

A. Component design

B. Route sheet

C. Time standards

D. All of these

What is the correct answer?

4

Under the Apprenticeship Act

A. All industries have to necessarily train the apprentices

B. Industries have to train apprentices according to their requirement

C. All industries employing more than 100 workers have to recruit apprentices

D. Only industries employing more than 500 workers have to recruit apprentices