Home
Current Affairs January 2024

What is the correct answer?

4

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

A. Consumes time, but no resources

B. Consumes resources but no time

C. Consumes neither time nor resources

D. Is a dangling event

Correct Answer :

C. Consumes neither time nor resources


Related Questions

What is the correct answer?

4

Work sampling is applied for

A. Estimation of the percentage utilisation of machine tools

B. Estimating the percentage of the time consumed by various job activities

C. Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible

D. All of the above

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if

A. Complete details of items in, waiting line are known

B. Arrival and waiting times are known and can be grouped to form a waiting line model

C. All variables and constants are known and form a linear equation

D. The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known

What is the correct answer?

4

The unit cost in case of batch production is ________ as compared to jobbing production.

A. Same

B. Low

C. High

D. None of these

What is the correct answer?

4

Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilisation

What is the correct answer?

4

Line organisation is suitable for

A. Sugar industries

B. Oil refining industries

C. Spinning and weaving industries

D. All of these

What is the correct answer?

4

Which of the following charts are used for plant layout design?

A. Operation process chart

B. Man machine chart

C. Travel chart

D. All of these

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

What is the correct answer?

4

The aim of value engineering is to

A. Find the depreciation value of a machine

B. Determine the selling price of a product

C. Minimise the cost without change in quality of the product

D. All of the above

What is the correct answer?

4

Routing is essential in the following type of industry

A. Assembly industry

B. Process industry

C. Job order industry

D. Mass production industry

What is the correct answer?

4

The chart which gives an estimate about the amount of materials handling between various work stations is known as

A. Flow chart

B. Process chart

C. Travel chart

D. Operation chart

What is the correct answer?

4

The main advantage of line organisation is its

A. Effective command and control

B. Defined responsibilities at all levels

C. Rigid discipline in the organisation

D. All of the above

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

Service time in queuing theory is usually assumed to follow

A. Normal distribution

B. Poissons distribution

C. Erlang distribution

D. Exponential law

What is the correct answer?

4

In product layout

A. Specialised and strict supervision is required

B. Machines can not be used to their maximum capacity

C. Manufacturing cost rises with a fall in the volume of production

D. All of the above

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

In breakeven analysis, total cost consists of

A. Fixed cost

B. Variable cost

C. Fixed cost + variable cost

D. Fixed cost + variable cost + overheads

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programmes

C. Is used for repetitive works

D. All of the above

What is the correct answer?

4

ABC analysis deals with

A. Analysis of process chart

B. Flow of material

C. Ordering schedule of job

D. Controlling inventory costs money

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

A-B-C analysis

A. Is a basic technique of materials management

B. Is meant for relative inventory control

C. Does not depend upon the unit cost of the item but on its annual consumption

D. All of the above