Home
Current Affairs January 2024

What is the correct answer?

4

PMTP (predetermined motion time systems) include

A. MTM (method time measurement)

B. WFS (work factor systems)

C. BNTS (basic motion time study)

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

At the breakeven point,

A. Total cost is more than the sales revenue

B. Total cost is less than the sales revenue

C. Total cost is equal to sales revenue

D. Fixed cost is equal to variable cost

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

Which of the following are the guidelines for the construction of a network diagram?

A. Each activity is represented by one and only one arrow in the network

B. Dangling must be avoided in a network diagram

C. Dummy activity consumes no time or resource

D. All of the above

What is the correct answer?

4

Linear programming can be applied successfully to

A. Chemical industry

B. Oil industry

C. Banks

D. All of these

What is the correct answer?

4

The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as

A. Job enlargement

B. Job enrichment

C. Job rotation

D. Job evaluation

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

What is the correct answer?

4

The work study is done by means of

A. Planning chart

B. Process chart

C. Stop watch

D. Any one of these

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

String diagram is used when

A. Team of workers is working at a place

B. Material handling is to be done

C. Idle time is to be reduced

D. All of the above

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Dispatching

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with the starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Scanlon Plan

B. Rowan Plan

C. Taylor Differential Piece Rate System

D. Halsey Premium Plan

What is the correct answer?

4

Standard time as compared to normal time is

A. Greater

B. Smaller

C. Equal

D. There is no such correlation

What is the correct answer?

4

Breakeven point is the point where

A. Fixed and variable cost lines intersect

B. Fixed and total cost lines intersect

C. Variable and total cost lines intersect

D. Sales revenue and total expensive lines intersect

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

The determination of standard time in a complex job system is best done through

A. Stop watch time study

B. Analysis of micro-motions

C. Grouping timing technique

D. Analysis of standard data system

What is the correct answer?

4

Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?

A. Halsey plan

B. Gantt plan

C. Rowan plan

D. Emerson's efficiency plan

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

CPM stands for

A. Combined Process Method

B. Critical Path Method

C. Common Planning Method

D. Critical Process Method

What is the correct answer?

4

Break-even analysis can be used for

A. Short run analysis

B. Long run analysis

C. Average of above two run analysis

D. There is no such criterion