Home
Current Affairs January 2024

What is the correct answer?

4

Process layout is employed for

A. Batch production

B. Continuous type of product

C. Effective utilisation of machines

D. All of the above

Correct Answer :

A. Batch production


Related Questions

What is the correct answer?

4

Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation

What is the correct answer?

4

A diagram showing the path followed by men and materials while performing a task is known as

A. String diagram

B. Flow process chart

C. Travel chart

D. Flow diagram

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

Travel charts are used to

A. Analyse material handling

B. Determine inventory control difficulties

C. Plan material handling procedure and routes

D. All of the above

What is the correct answer?

4

The value engineering technique in which experts of the same rank assemble for product development is called

A. Delphi

B. Brain storming

C. Morphological analysis

D. Direct expert comparison

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

Work study is most useful

A. Where production activities are involved

B. In judging the rating of machines

C. In improving industrial relations

D. In judging the output of a man and improving it

What is the correct answer?

4

Performance rating is equal to

A. Observed performance + normal performance

B. Observed performance - normal performance

C. Observed performance × normal performance

D. None of the above

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method

What is the correct answer?

4

Inventory management consists of

A. Effective running of stores

B. State of merchandise methods of storing and maintenance etc.

C. Stock control system

D. All of the above

What is the correct answer?

4

Father of time study was

A. F.W. Taylor

B. H.L. Gantt

C. F.B. Gilbert

D. R.M. Barnes

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The deductions for, employees provident fund start

A. Immediately on joining the service

B. After 60 days of joining the service

C. After 100 days of joining the service

D. After 240 days of joining the service

What is the correct answer?

4

The product layout

A. Lowers overall manufacturing time

B. Requires less space for placing machines

C. Utilises machine and labour better

D. All of these

What is the correct answer?

4

Expediting function consists in keeping a watch on

A. Operator's activity

B. Flow of material and in case of trouble locate source of trouble

C. Minimising the delays

D. Making efficient despatching

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

Which of the following type of layout is suitable for automobile manufacturing concern?

A. Product layout

B. Process layout

C. Fixed position layout

D. Combination layout

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

Queuing theory is associated with

A. Sales

B. Inspection time

C. Waiting time

D. Production time

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Bin card is used in

A. Administrative wing

B. Workshop

C. Foundry shop

D. Stores

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from noncritical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All of the above

What is the correct answer?

4

Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity