Home
Current Affairs January 2024

What is the correct answer?

4

Queueing theory is used for

A. Inventory problems

B. Traffic congestion studies

C. Job-shop scheduling

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

PERT and CPM are

A. Techniques to determine project status

B. Decision making techniques

C. Charts which increase aesthetic appearance of rooms

D. Aids to the decision maker

What is the correct answer?

4

Direct expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. None of these

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as

A. Dry work Plan

B. Halsey Premium Plan

C. Taylor Plan

D. Rowan Plan

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All of the above

What is the correct answer?

4

PERT analysis is based upon

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack

What is the correct answer?

4

If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then breakeven point is equal to

A. (F × V)/P

B. (F × P)/V

C. F/[1 + (V/P)]

D. F/[1 - (V/P)]

What is the correct answer?

4

Gantt charts are used for

A. Forecasting sales

B. Production schedule

C. Scheduling and routing

D. Linear programming

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

Value engineering aims at finding out the

A. Depreciation value of a product

B. Resale value of a product

C. Major function of the item and accomplishing the same at least cost without change in quality

D. Breakeven point when machine requires change

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

Break-even analysis shows profit when

A. Sales revenue > total cost

B. Sales revenue = total cost

C. Sales revenue < total cost

D. Variable cost < fixed cost

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

String diagram is used

A. For checking the relative values of various layouts

B. When a group of workers are working at a place

C. Where processes require the operator to be moved from one place to another

D. All of the above

What is the correct answer?

4

PERT/CPM, techniques can be used for following applications

A. Once through project

B. Maintenance jobs

C. Research and development

D. All of the above

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

The difference between the time available to do the job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

Gantt chart provides information about the

A. Material handling

B. Proper utilisation of manpower

C. Production schedule

D. Efficient working of machine

What is the correct answer?

4

The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as

A. Event

B. Free float

C. Artificial

D. Dummy

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Works cost implies

A. Primary cost

B. Factory cost

C. Factory expenses

D. Primary cost + factory expenses

What is the correct answer?

4

In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if

A. Complete details of items in, waiting line are known

B. Arrival and waiting times are known and can be grouped to form a waiting line model

C. All variables and constants are known and form a linear equation

D. The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles