Light construction
Heavy construction
Industrial construction
None of these
B. Heavy construction
Site investigation started
Sessional work completed
Bus starts from Jaipur
Class is being attended
500 cum
1000 cum
1500 cum
2000 cum
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling
An engineer
An architect
An owner
All the above
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
Site survey
Availability of construction materials
Availability of labour
All the above
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
1880
1900
1920
1940
Only (i) is correct
(i) and (ii) are correct
(i) and (iii) are correct
(ii) and (iii) are correct
Drag line
Hoe
Clam shell
Dipper shovel
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
(a + m + b)/6
(a + 2m + b)/6
(a + 4m + b)/6
(a + 5m + b)/6
Should invest in neither of the two projects
Could invest in either of the two projects
Should invest in project A
Should invest in project B
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
Total float and free float
Total float and independent float
Free float and independent float
None of the above
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
Bar chart method
Milestone chart
Critical path method (CPM)
Programme Evaluation and Review Technique (PERT)
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity
1910
1920
1930
1940
1-2 is 4
2-3 is 7
3-4 is 8
All the above
Line organisation
Line and staff organisation
Functional organisation
None of these
Change of critical path
Decrease of project completion time
Increase of project completion time
All of the above
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Hoe
Shovel
Dragline
None of the above
Is always longest
Is always shortest
May be longest
May be shortest
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
All the above
Determines the status of each activity
Adjusts automatically changes in activity progress
Is a dynamic system
None of these