Annual cost method
Rate of return method
Total life average method
Any one of the above
D. Any one of the above
Batch production
Job production
Mass production
All of the above
Complicated items only
Simple items only
Crash programmer items only
Any item
Stop watch time study
Analysis of micro-motions
Grouping timing technique
Analysis of standard data system
Loads are uniform
Routes do not vary
Materials move relatively continuously
All of these
Job production
Batch production
Mass production
All of these
Principle of overall integration
Principle of flow
Principle of flexibility
All of these
That can't be analysed mathematically
Involving multistage queuing
To verify mathematical results
All of the above
Relative worth of jobs
Skills required by a worker
Contribution of a worker
Contribution of a job
The minimum time required for completion of project
The maximum time required for completion of project
Maximum cost required for completion of project
Minimum cost required for completion of project
Actions of operator
Layout of work place
Tooling and equipment
All of the above
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
Strict adherence to specification
Separation of planning and design part
Each individual maintains functional efficiency
All of the above
Optimum lot size
Highest level of inventory
Lot corresponding to breakeven point
Capability of a plant to produce
Batch production
Continuous production
Effective utilization of machine
All of the above
Operation
Inspection
Delay/ temporary Storage
Permanent storage
String diagram
Flow process chart
Travel chart
Flow diagram
Factory expenses
Selling expenses
Administrative expenses
None of these
Time oriented technique
Event oriented technique
Activity oriented technique
Target oriented technique
CPM
PERT
Inventory control
All of these
Maximum float
Minimum float
Zero float
Average float
Job production
Automatic production
Continuous production
Intermittent production
Latest start time of succeeding event earliest finish time of preceding event activity time
Latest start time of the event earliest start time of the event
Latest finish time of event earliest finish time of the event
Anyone of the above
Synthesising in concepts
Is built of activities oriented programmes
Is used for repetitive works
All of the above
Early finish
Early start
Late start
Late finish
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with starting of processes
Regulates the progress of job through various processes
Determine standard costs
Determine the number of machines a person may run
Provide a basis for setting piece price or incentive wages
All of the above
Taylor
Drucker
McGregor
Galileo
Depreciation value of a product
Resale value of a product
Major function of the item and accomplishing the same at least cost without change in quality
Breakeven point when machine requires change
Improving a work method
Improvising a work method
Designing a work method
Reducing inventory costs
Maximum slack
Minimum slack
Zero slack
Average slack