Home
Current Affairs January 2024

What is the correct answer?

4

Replacement studies are made on the following basis:

A. Annual cost method

B. Rate of return method

C. Total life average method

D. Any one of the above

Correct Answer :

D. Any one of the above


Related Questions

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

The determination of standard time in a complex job system is best done through

A. Stop watch time study

B. Analysis of micro-motions

C. Grouping timing technique

D. Analysis of standard data system

What is the correct answer?

4

For material transportation, conveyors are used when the prevailing conditions include

A. Loads are uniform

B. Routes do not vary

C. Materials move relatively continuously

D. All of these

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

According to Muther, the basic principle of best layout is

A. Principle of overall integration

B. Principle of flow

C. Principle of flexibility

D. All of these

What is the correct answer?

4

Monte Carlo solutions in queuing theory are extremely useful in queuing problems

A. That can't be analysed mathematically

B. Involving multistage queuing

C. To verify mathematical results

D. All of the above

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

What is the correct answer?

4

The critical path of a network represents

A. The minimum time required for completion of project

B. The maximum time required for completion of project

C. Maximum cost required for completion of project

D. Minimum cost required for completion of project

What is the correct answer?

4

Motion study involves analysis of

A. Actions of operator

B. Layout of work place

C. Tooling and equipment

D. All of the above

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specification

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All of the above

What is the correct answer?

4

In inventory control, the economic order quantity is the

A. Optimum lot size

B. Highest level of inventory

C. Lot corresponding to breakeven point

D. Capability of a plant to produce

What is the correct answer?

4

Product layout is employed for

A. Batch production

B. Continuous production

C. Effective utilization of machine

D. All of the above

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

A diagram showing the path followed by men and materials while performing a task is known as

A. String diagram

B. Flow process chart

C. Travel chart

D. Flow diagram

What is the correct answer?

4

Direct expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. None of these

What is the correct answer?

4

CPM is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

A-B-C analysis is used in

A. CPM

B. PERT

C. Inventory control

D. All of these

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. Average float

What is the correct answer?

4

Emergency rush order can be pushed more effectively in

A. Job production

B. Automatic production

C. Continuous production

D. Intermittent production

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programmes

C. Is used for repetitive works

D. All of the above

What is the correct answer?

4

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A. Early finish

B. Early start

C. Late start

D. Late finish

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

Value engineering aims at finding out the

A. Depreciation value of a product

B. Resale value of a product

C. Major function of the item and accomplishing the same at least cost without change in quality

D. Breakeven point when machine requires change

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack