Home
Current Affairs January 2024

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

Correct Answer :

A. Flow of material in the plant


Related Questions

What is the correct answer?

4

String diagram is used

A. For checking the relative values of various layouts

B. When a group of workers are working at a place

C. Where processes require the operator to be moved from one place to another

D. All of the above

What is the correct answer?

4

A systematic job improvement sequence will consist of

A. Motion study

B. Time study

C. Job enrichment

D. All of these

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

An optimum project schedule implies

A. Optimum utilization of men, machines and materials

B. Lowest possible cost and shortest possible time for project

C. Timely execution of project

D. To produce best results under given constraints

What is the correct answer?

4

P.M.T.S. (Predetermined Motion Time Systems) include

A. M.T.M. (Method Time Measurement)

B. W.F.S. (Work Factor Systems)

C. B.M.T.S. (Basic Motion Time Study)

D. All of these

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as

A. Job enlargement

B. Job enrichment

C. Job rotation

D. Job evaluation

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

In A-B-C analysis, which class of items are generally large in number?

A. A

B. B

C. C

D. None of these

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

The critical path of a network represents

A. The minimum time required for completion of project

B. The maximum time required for completion of project

C. Maximum cost required for completion of project

D. Minimum cost required for completion of project

What is the correct answer?

4

In Halsey 50-50 plan, output standards are established

A. By time study

B. From previous production records

C. From one's judgement

D. All of the above

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

Motion study involves analysis of

A. Actions of operator

B. Layout of work place

C. Tooling and equipment

D. All of the above

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

What does symbol 'D' imply in work study?

A. Inspection

B. Transport

C. Delay/temporary storage

D. Permanent storage

What is the correct answer?

4

Gantt chart provides information about the

A. Material handling

B. Proper utilisation of manpower

C. Production schedule

D. Efficient working of machine

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

A big advantage of PERT over Gantt charts is that in the former case

A. Activities and events are clearly shown

B. Early start and late finish of an activity are clearly marked

C. Activity times are clear

D. Interrelationship among activities is clearly shown.

What is the correct answer?

4

Work study involves

A. Only method study

B. Only work measurement

C. Method study and work measurement

D. Only motion study

What is the correct answer?

4

In the Halsey system of wage incentive plan, a worker is

A. Paid as per efficiency

B. Ensured of minimum wages

C. Not paid any bonus till his efficiency

D. Never a loser

What is the correct answer?

4

Probabilistic time for completion of any activity can be found out from

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of these

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Which one of the following techniques is used for determining allowances in time study?

A. Acceptance sampling

B. Linear regression

C. Performance rating

D. Work sampling

What is the correct answer?

4

Time study is carried out

A. By finding all the significant informations regarding the job, work place and machine tool etc.

B. By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

C. By observing and recording the time taken by the operator for an operation

D. All of the above

What is the correct answer?

4

Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilisation