Home
Current Affairs January 2024

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

Correct Answer :

C. Probability


Related Questions

What is the correct answer?

4

The critical path of a network represents

A. The minimum time required for completion of project

B. The maximum time required for completion of project

C. Maximum cost required for completion of project

D. Minimum cost required for completion of project

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programmes

C. Is used for repetitive works

D. All of the above

What is the correct answer?

4

Material handling and plant location is analysed by

A. Gantt chart

B. Bin chart

C. Emerson chart

D. Travel chart

What is the correct answer?

4

Inventory management consists of

A. Effective running of stores

B. State of merchandise methods of storing and maintenance etc.

C. Stock control system

D. All of the above

What is the correct answer?

4

Which of the following is not wage incentive plan?

A. Differential piece rate system

B. Rowan plan

C. Emerson plan

D. Taylor plan

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of any project is known as

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling

What is the correct answer?

4

Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

What is the correct answer?

4

What does symbol 'D' imply in work study?

A. Inspection

B. Transport

C. Delay/temporary storage

D. Permanent storage

What is the correct answer?

4

Works cost implies

A. Primary cost

B. Factory cost

C. Factory expenses

D. Primary cost + factory expenses

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

Percent idle time for men or machines is found by

A. Work sampling

B. Time study

C. Method study

D. Work study

What is the correct answer?

4

In CPM, the cost slope is determined by

A. Crash cost/Normal Cost

B. (Crash Cost - Normal cost)/ (Normal time - Crash time)

C. Normal Cost/Crash cost

D. (Normal cost - Crash cost)/ (Normal time - Crash time)

What is the correct answer?

4

For ship vessel industry the following layout is best suited

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Critical Path Net Work helps an engineer

A. To concentrate his attention on critical activities

B. To divert the resources from noncritical advanced activities to critical activities

C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

D. All of the above

What is the correct answer?

4

Graphical method, simplex method, and transportation method are concerned with

A. Breakeven analysis

B. Value analysis

C. Linear programming

D. Queueing theory

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

Critical path on PERT/CPM chart is obtained by joining the events having

A. Maximum slack

B. Minimum slack

C. Average slack

D. No slack

What is the correct answer?

4

In manufacturing management, the term 'Dispatching' is used to describe

A. Dispatch of sales order

B. Dispatch of factory mail

C. Dispatch of finished product of the user

D. Dispatch of work orders through shop floor

What is the correct answer?

4

One of the basic essentials of an incentive plan is that

A. A differential piece rate system should exist

B. Minimum wages should be guaranteed

C. Provide incentive to group efficiency performance

D. All standards should be based on time studies

What is the correct answer?

4

In micro-motion study, therblig is described by

A. A symbol

B. An event

C. An activity

D. Standard symbol and colour

What is the correct answer?

4

A-B-C analysis is used in

A. CPM

B. PERT

C. Inventory control

D. All of these

What is the correct answer?

4

Pick up the correct statement from the following

A. Critical path method is an improvement upon bar chart method

B. Critical path method provides a realistic approach to the daily problems

C. Critical path method avoids delays which are very common in bar chart

D. All of the above

What is the correct answer?

4

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A. Early finish

B. Early start

C. Late start

D. Late finish

What is the correct answer?

4

The work study is done by means of

A. Planning chart

B. Process chart

C. Stop watch

D. Any one of these

What is the correct answer?

4

The probability distribution of project completion in PERT follows following distribution

A. Normal

B. Binomial

C. Exponential

D. Gaussian

What is the correct answer?

4

A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the

A. Fixed cost line

B. Variable cost line

C. Total cost line

D. Sales revenue line

What is the correct answer?

4

Micro-motion study involves following number of fundamental hand motions

A. 8

B. 12

C. 16

D. 20